Six Year Mine Life at Mineral Hill
Released
Released
Announcement PDF
ASX/Media Announcement
30 September 2024
Six Year Mine Life at Mineral Hill
Building the foundation for a long-term gold and copper operation
Highlights:
•
Initial Underground Ore Reserve: 0.7Mt for 0.8% Cu, 1.4g/t Au, 20g/t Ag, 1.9% Pb and 1.6% Zn.
•
Updated Open Pit Ore Reserve: Estimates updated for the Pearse pits using A$2,859/oz gold price.
•
Production Target extended to 2030: Six-year life of mine (LOM) plan incorporating Ore Reserves
and Mineral Resource inventory.
•
Gold & Copper expected to account for 85% of life of mine metal production with copper production
to commence in FY26.
Kingston Resources Limited (ASX:KSN) (‘Kingston’, or ‘The Company’) is pleased to announce the release
of a maiden Ore Reserve for the underground Resources at Mineral Hill. An updated open pit Ore Reserve
is also included in this announcement, underpinned by the recent Mineral Resource update at Pearse North,
revised metal pricing and other modifying factors.
The underground Ore Reserve marks a pivotal milestone for Kingston, delivering a substantial boost in
technical and financial certainty. Through extensive technical studies, the company has effectively minimised
operational risks and established a solid foundation for future growth. Kingston confidently views this as the
launchpad for the expansion of the life of mine at Mineral Hill as operations will pivot to underground mining
following the current open pit mining operations.
Production Target Highlights:
•
•
•
•
•
Open pit and underground mining scheduled out to 2030.
Ore Reserves in the mine plan of 1.1Mt.
Open pit mining of 0.5Mt @ 2.8g/t Au and 47g/t Ag.
Underground mining of 1.7Mt @ 2.0g/t Au, 12g/t Ag, 0.9% Cu, 1.2% Pb and 0.9% Zn.
LOM production of 207koz gold equivalent (AuEq) payable (see Table 4 for the metal split)
Kingston Resources Managing Director, Andrew Corbett, comments:
“We are thrilled to announce the significant progress we have made at Mineral Hill. The extension of our mine
life to 2030 is a significant step forward, strongly supported by the increase in Ore Reserves to 1.1Mt. This
achievement is testament to our team’s commitment to sustainable, long-term value creation.
We have now firmed up a strong mine plan that is backed by comprehensive metallurgical and engineering
studies. As we build cash from our open pit mining operations, our focus will shift to extensional drilling to
grow the life of mine and support the central west community well into the future. Kingston is well positioned
with a fully approved and operating mine, high-grades, extended mine life, and abundant resource growth
opportunities.”
ASX: KSN
Shares on Issue: 707M
Market Cap: A$61M
Cash: (30 June 2024) A$8.36m
202/201 Miller Street,
North Sydney, NSW 2060
+61 2 8021 7492
info@kingstonresources.com.au
www.kingstonresources.com.au
@KSNResources
CAUTIONARY STATEMENT
The LOM Production Target is based on Probable Ore Reserve estimates for the Pearse open pits and the
Southern Ore Zone (SOZ). Additionally, Mineral Resources from Pearse open pits, SOZ and Jack’s Hut have
been used to estimate the Production Target.
The estimated Ore Reserves and Mineral Resources underpinning the Production Target have been
prepared by Competent Persons in accordance with the requirements in the JORC Code.
All material assumptions on which the Production Target is based are detailed in the Mineral Resource and
Ore Reserve sections included in this announcement and in the original technical reports included in the
appendices. While Kingston considers all the material assumptions to be based on reasonable grounds, there
is no certainty that they will prove to be correct or that the range of outcomes indicated by the Production
Target will be achieved.
The Production Target comprises 51% Ore Reserves, 11% Measured & Indicated Resources and 38%
Inferred Resources. The first 12 and 36 months of the Production Target are underpinned by 89% and 80%
of Measured and Indicated Resources respectively.
Table 1: Life of mine Production Target by resource category
Source
Tonnes Mined
(mt)
% Measured and
Indicated
Gold
g/t
Silver
g/t
Copper
%
Lead
%
Zinc
%
Open Pit
0.4
91%
3.5
49
-
-
-
Underground
1.7
55%
2.0
12
0.9%
1.2%
0.9%
Full Production Target
2.1
62%
There is a low level of geological confidence associated with Inferred Resources and there is no certainty
that further exploration work will result in the determination of Indicated Resources or that the Production
Target itself will be realised.
The Company notes that the Project forecasts a positive financial performance under a scenario where only
the Ore Reserve component is mined. Inclusion of Inferred Resources in Production Target reporting is not
the determining factor in overall Project viability and it is reasonable to report the LOM plan with Inferred
Resources.
The Company has concluded that it is has a reasonable basis for providing the forward-looking statements
included in this announcement. The detailed reasons for that conclusion are outlined throughout this
announcement. See section titled IMPORTANT NOTICES for additional information.
www.kingstonresources.com.au
2
PRODUCTION TARGET SUMMARY
Mine plans were prepared based on the open pit and underground Ore Reserves included in this
announcement and as a separate Life of Mine production target which includes a portion of Inferred resources
within the open pit designs and underground stopes.
Table 2: Open pit Production Target physicals.
Open Pit Mining
Oxide Tonnes
Sulphide Tonnes
Ore Tonnes
Grades
Gold
Silver
Metal
Gold
Silver
Material Movement
Waste Tonnes
Ore Tonnes
Material Movement
Strip Ratio
Processing
Gold Processing Recovery
Recovered Gold
Recovered Silver
Unit
kt
kt
kt
Open Pit
79
443
522
g/t
g/t
2.8
47
koz
koz
47
791
kt
kt
kt
W:O
3,453
522
3,975
7
%
koz
koz
80%
38
516
Table 3: Underground Production Target physicals.
Underground Mining
Mining
Development Ore Tonnes
Stope Ore Tonnes
Total Ore Tonnes
Grades
Gold
Silver
Copper
Lead
Zinc
Metal
Gold
Silver
Copper
Lead
Zinc
Material Movement
Waste Tonnes
Ore Tonnes
Material Movement
www.kingstonresources.com.au
Unit
Underground
kt
kt
kt
211
1,485
1,696
g/t
g/t
%
%
%
2.0
12
0.9%
1.2%
0.9%
koz
koz
kt
kt
kt
107
664
15
20
15
kt
kt
kt
484
1,696
2,180
3
Mineral Hill has now fully transitioned to hard rock mining, with open pit mining underway in the Pearse North
open pit. Both Pearse North and Pearse South will be mined by conventional drill and blast methods using
hydraulic excavators and mining trucks.
Processing of the oxide ore commenced during August 2024 upon the recommissioning of the crushing and
grinding circuits. Open pit mining will be sequenced by focusing initially on Pearse North, followed by a
cutback and deepening of the existing pit at Pearse South. Initial output from the open pit ore will be gold/silver
dore from the oxide at Pearse North, followed by production of a gold/silver concentrate from both pits. The
commissioning and operation of the flotation circuit will be finalised in Q2FY25. The open pit Ore Reserve
estimate is included in this announcement and lists out the material assumptions used to generate the
production target.
Table 4: Life of mine Production Target physicals.
Open Pit Ore Reserve
Mt
0.35
Open Pit Mineral Resource
Mt
0.19
Underground Ore Reserve
Mt
0.7
Underground Mineral Resource
Mt
1.0
Total Life of Mine
Mt
2.2
Annual Processing Rate
ktpa
380
Payable Gold
koz
117
Payable Copper
kt
12
Payable Silver
koz
858
Payable Lead
kt
11
Payable Zinc
kt
6
AuEq Payable Ounces
koz
207
Gold Price
US$/oz
1,944
Silver Price
US$/oz
24
Copper Price
US$/lb
4.30
Lead Price
US$/lb
0.95
Zinc Price
US$/lb
1.19
AUD:USD
0.68
The non-Reserve component of the reported Production Target comprising Mineral Resources
includes adjustment of tonnes and grade by application of Modifying Factors.
The Production Target is being reported from 1 October 2024
Access to the underground workings has already been established, with pumping and rehabilitation of the
access drive to the Southern Ore Zone (SOZ) completed at the start of the year. Resource definition drilling
is due to commence in March 2025 Quarter. Underground development and mining are forecast to
commence in the second half of 2025, delivering base metal ore to the ROM pad for processing. SOZ will be
the primary production centre in the early phase, followed by the addition of Jack’s Hut.
The SOZ Ore Reserve estimate and Life of Mine Production Target are based on bottom-up mining by long
hole stoping and uncemented rock fill. Access will be via the existing Eastern Decline with its portal in the
Eastern Ore Zone (EOZ) Pit. The SOZ production rate will be approximately 30,000t per month.
www.kingstonresources.com.au
4
Dec-30
Jun-30
Dec-29
Jun-29
Dec-28
Jun-28
Dec-27
Jun-27
Dec-26
Jun-26
Dec-25
Jun-25
Dec-24
Jun-24
Dec-23
Jul-23
Process Plant Refurbishment
Process Plant Commissioning
Open Pit Mining
Open Pit Processing
UG Pre-Production Development
UG Mining
UG Processing
Figure 1: LOM mining and processing schedule overview.
Mined Tonnage (kt)
425
450
388
400
382
345
350
325
300
300
250
200
150
96
100
50
0
FY25
FY26
FY27
FY28
Open Pit Mining
UG Mining
FY29
FY30
FY31
Total Mined Tonnes
Figure 2: Mineral Hill life of mine schedule.
Payable Metal (koz AuEq)
45
40
40
36
36
36
35
30
25
24
24
20
15
12
10
5
FY25
FY26
FY27
Gold
Copper
FY28
Silver
Lead
FY29
Zinc
FY30
FY31
AuEq oz
Figure 3: LOM forecast of payable metal.
www.kingstonresources.com.au
5
OPEN PIT ORE RESERVE ESTIMATION
Open Pit Mining Summary
The Ore Reserves are based on extraction by open pit mining from two adjacent pits. The Pearse South Pit
will be a pushback of an existing pit. The Pearse North Pit is a new development.
The Pearse orebodies comprise mainly sulphide and transitional gold/silver mineralisation with some minor
oxide material. The sulphide and transitional ore will be processed by flotation to produce a precious metal
concentrate for sale. The oxide ore and flotation tailings will be leached in a CIL circuit to produce dore. The
majority of the value in both the concentrate and dore comes from the gold.
Table 5 Pearse Ore Reserves Summary
Cut
Tonnes
off
kt
Au g/t
Pit
Pearse South
Probable Ore
Oxide
Sulphide/Transition
Subtotal
Waste
Waste:Ore Ratio
Pearse North
Probable Ore
Oxide
Sulphide/Transition
Subtotal
Waste
Waste:Ore Ratio
Total
Probable Ore
Oxide
Sulphide/Transition
Subtotal
Waste
Waste:Ore Ratio
Au
g/t
Ag
g/t
Sb
ppm
As
ppm
S
%
Au
koz
Ag
koz
1.5
0
19
19
0
370
370
0
250
250
0
620
620
0.8
1.5
0
140
140
1,930
14.1
0.0
4.3
4.3
0
85
85
0.8
1.3
10
220
240
2,200
9.3
2.5
3.2
3.2
10
34
33
1,220
727
0.7
1
23
24
10
360
370
4,130
11.1
2.5
3.6
3.6
10
53
52
1,770
451
0.4
1
42
43
2,680
2,911
2.
3.
4.
5.
Notes:
The tonnes and grades shown in the totals rows are stated to a number of significant figures reflecting the confidence of the estimate. The
table may nevertheless show apparent inconsistencies between the sum of components and the corresponding rounded totals.
There are no Proved Ore Reserves.
Probable Ore Reserves are derived from Indicated Mineral Resources.
The Ore Reserves do not include, or depend upon, Inferred Mineral Resources.
The Ore Reserves form part of the Mineral Resources.
6.
The reference point is the mill feed at the primary crusher and includes consideration for operational modifying factors.
1.
www.kingstonresources.com.au
6
Figure 4: Pearse North open pit mining operations.
Changes from previous Ore Reserves Estimate
Kingston previously released an Ore Reserves Estimate for the Pearse deposits in the ASX Release “Pearse
Open Pit – Ore Reserve Update” dated 15 March 2023. The open pit Ore Reserves Estimate in this
announcement is an update of the March 2023 estimate. Key changes in this update include:
•
The inclusion of an updated Mineral Resource Estimate for Pearse North which included further
drilling and a revised geological interpretation (see ASX Announcement dated 14 May 2024).
•
Long term gold price forecast has increased from A$2,571/oz in March 2023 to A$2,859/oz in June
2024.
•
Revision of gold and silver payabilities as well as concentrate land and sea transport from information
provided by commodity brokers. The exact terms of the payabilities are commercially sensitive for
both Kingston and its trading partners.
•
Revised application of metallurgical test results from the test work conducted on Pearse North ore.
Pearse South metallurgy is still based on the historical performance, so separate recovery parameters
are now used for both pits.
•
Revision of the mining, processing and site administration unit costs at a higher level of confidence
as a result of the inclusion of actual costs from the ongoing mining and processing operations.
www.kingstonresources.com.au
7
•
Further detailed geotechnical assessment has been conducted for the slip area on the east wall of
Pearse South Pit.
Table 6 Changes from Mar-2023 to June-2024.
Pit
Pearse South
Oxide kt
Oxide Au g/t
Oxide Ag g/t
Fresh kt
Fresh Au g/t
Fresh Ag g/t
Waste kt
Pearse North
Oxide kt
Oxide Au g/t
Oxide Ag g/t
Fresh kt
Fresh Au g/t
Fresh Ag g/t
Waste kt
Total
Oxide kt
Oxide Au g/t
Oxide Ag g/t
Fresh kt
Fresh Au g/t
Fresh Ag g/t
Waste kt
Contained Metal
Gold koz
Siver koz
Mar-23
Jun-24
Change
Change %
0
0.0
0
140
4.0
84
1,660
0
0.0
0
140
4.3
85
1,930
0
0.0
0
0
0.3
1
270
0%
0%
0%
0%
8%
1%
16%
10
2.4
5
110
3.4
26
1,010
10
2.5
10
220
3.2
34
2,200
0
0.1
5
110
-0.2
8
1,190
0%
4%
100%
100%
-6%
31%
118%
10
2.4
5
250
3.8
58
2,670
10
2.5
10
360
3.6
53
4,130
0
0.1
5
110
-0.2
-5
1,460
0%
4%
100%
44%
-5%
-9%
55%
31
470
43
620
12
150
39%
32%
Criteria Used for Classification
Only Indicated Mineral resources are considered in the Ore Reserve Estimate. There are no Measured
resources in the current Mineral Resource Estimate. Probable Ore Reserves are derived only from Indicated
Mineral Resources.
In the opinion of the Competent Person, when taken as a whole, the modifying factors have been defined to
a level of confidence commensurate with a Probable Ore Reserve. There are no issues currently identified
which are likely to have a material impact on the viability of the project and the Ore Reserves as stated.
Mining Method and Assumptions
Open cut mining will be by conventional drill and blast methods using hydraulic excavators and mining trucks.
Pearse North is a new pit and Pearse South Pit will be a pushback and deepening of the existing pit.
Commencement of mining in Pearse South is timed so that Pearse North can continue to supply ore until the
Pearse South pushback reaches the depth of the main ore benches. There will be a period when the mining
fleet is shared between the two pits which are 350 metres apart.
www.kingstonresources.com.au
8
Dilution was modelled by re-blocking the resource model to 2.5 x 2.5 x 2.5 metre blocks. This is the planned
mining flitch height and is coarser than the narrowest mining widths reported anecdotally. Compared to the
original sub-blocked resource model, the re-blocked version shows approximately 20% dilution at low gold
grade and 5% ore loss.
Kingston will mine the two Pearse pits using the company’s own operators with a hired fleet and contract drill
and blast.
Mining costs are from the current project budget based on actual wages, fleet hire costs, the drill and blast
contract and additional costs such as grade control. The life of mine opencut mining cost in the financial
model is A$7.28 per tonne of ore and waste.
Processing Methods for the Open Pits
Pearse North and South are both gold / silver deposits and have the same mineralisation style. Apart from a
small tonnage of oxide mineralisation in Pearse North, all the ore is transitional or fresh (sulphide). Oxide ore
will be processed to gold / silver dore using the existing CIL circuit. Using oxide process records from 2015
and recent process assessments, KSN estimates an oxide CIL recovery 85% for gold and 79% for silver.
The process route for sulphide ore is:
•
Crushing / grinding / flotation to produce a gold / silver concentrate for sale.
•
CIL recovery of gold and silver from the flotation tailings.
The metallurgical recoveries for each of these process routes is detailed in Table 7.
Open Pit Ore Reserve Estimation Methodology
The Ore Reserve Estimate was undertaken by initially undertaking an optimisation study over the resources
with the key inputs outlined in this announcement. Mining design was subsequently undertaken with
consideration of geotechnical and mining parameters.
The Basis of the Cutoff Grade and Material Modifying Factors
Cutoff grades were calculated separately for both oxide and sulphide material. Both were determined by
calculating the gold head grade which covers the costs of processing, site administration, concentrate
transport, payabilities, gold refining and royalties. Silver was included in the calculation by reporting the
average silver to gold ratio for each deposit.
The oxide cutoff is 0.8 g/t Au and sulphide cutoff grades are 1.50 g/t Au for Pearse South and 1.30 g/t Au for
Pearse North. The key factors used to determine the open pit cutoff grades and other material modifying
factors are generally considered to be at least at a pre-feasibility level of assessment, with support from
current operational data. Key factors considered in the preparation of the Ore Reserve estimate are listed in
Table 7.
Table 7: Key modifying factors for the Pearse open pit Ore Reserve estimates.
Modifying Factor
Basis
Processing and Site
Administration Costs
Updates in 2024 of process and site G&A operating costs using data
from the tailings retreatment operation and current preparations for
sulphide ore processing.
Metallurgical Recovery
Oxide CIL recovery is estimated at 85% for gold and 79% for silver,
based on process records from 2015.
www.kingstonresources.com.au
9
Estimated recoveries to concentrate for the two pits average 65% for
gold and 65% for silver.
CIL recoveries of 10% for gold and 8% for silver were applied to
flotation tailings based on 2015 / 2016 production records.
Commodity Prices
Gold and silver prices are based on a consensus forecast for calendar
years 2024 to 2028. Gold is set at US$1,944/oz and silver at US$24/oz
and long-term A$:US$ exchange rate at 0.68.
Contaminant concentrations
Concentrate contaminant grades are expected to average 2.3% As
and 1.0% Sb. These grades will not incur penalties.
Royalties
NSW Government ad valorem formula with a 4% base royalty. An
additional 2% NSR royalty is paid to Quintana.
SOZ MINERAL RESOURCE UPDATE
The Mineral Resource estimate for the Southern Ore Zone (SOZ) has been updated to include the additional
11 diamond drill holes completed by Kingston during 2023-2024. This drilling primarily focused on the A-Lode
mineralisation and so this lode has been the primary change since the 2022 estimate.
The 2024 SOZ Mineral Resource Estimate as at 1 June 2024 is shown in Table 8.
.
Table 8. SOZ Mineral Resource Summary (> A$50 NVPT)
* Due to rounding to appropriate significant figures, minor discrepancies may occur, tonnages are dry metric tonnes.
Mineral Resources are not Ore Reserves and do not have demonstrated economic viability.
Inferred resource have less geological confidence than Measured or Indicated resources and should not have
modifying factors applied to them. It is reasonable to expect that with further exploration most of the inferred
resources could be upgraded to indicated resources.
Changes from previous Mineral Resource Estimate
In comparison to the 2022 SOZ MRE (see ASX Announcement on 22 November 2022), the most significant
factors influencing the 2024 estimate include:
•
Inclusion of the 2023-2024 drilling results.
•
Updated A-Lode geological interpretation.
•
Inclusion of material outside the High-Grade wireframed lodes (i.e. within Lode_ID 53).
•
Change in metal pricing.
•
Metallurgical assumptions within the NVPT formula.
The inherent assumption in 2022 was that saleable copper, lead and zinc concentrates (and dore) could be
produced from all lodes within the deposit, despite some of the lodes having very low head grades for some
www.kingstonresources.com.au
10
of the metals. In the updated 2024 estimate, the type of concentrate products produced would depend on the
lode being mined. Certain lodes may produce a copper concentrate only, as it would not be feasible to
economically produce a lead and zinc concentrate. These changes have been brought into effect within the
NVPT formula which is used to state the resources.
In terms of tonnage, the 2024 MRE has no material difference compared to the 2022 estimate (Table 9, Table
10). Gold and copper grades have increased materially overall (10% and 42%). Grades within the Measured
and Indicated portions have all increased except for copper, which has reduced by 2%. The change in the
NVPT formula has allowed for a selection of higher value material and provided greater certainty on the
potential for eventual economic extraction.
Table 9: 2022 SOZ Mineral Resource Estimate.
Table 10: Percentage difference between the 2022 and 2024 Mineral Resources.
Classification
Measured
Indicated
Inferred
Total
Tonnes
Meas + Ind
2%
3%
-4%
-1%
3%
Cu Grade Pb Grade Zn Grade Au Grade Ag Grade Cu Metal Pb Metal Zn Metal Au Metal Ag Metal
-5%
-4%
14%
-4%
-1%
-3%
0%
14%
-2%
1%
-3%
21%
14%
7%
16%
-1%
25%
17%
10%
19%
27%
-51%
-60%
85%
-40%
21%
-53%
-62%
78%
-43%
10%
-15%
-25%
42%
-13%
9%
-15%
-25%
41%
-14%
-2%
24%
17%
8%
18%
-2%
24%
17%
8%
18%
Geology and Geological Interpretation
The mineralisation style at SOZ is an epithermal to mesothermal polymetallic (Cu–Au to Cu-Pb-Zn-Ag-Au
system) vein and breccia system hosted by the Late Silurian to Early Devonian Mineral Hill Volcanics.
Mineralisation is structurally controlled and comprises lodes centred on hydrothermal breccia zones within
and adjacent to numerous faults, surrounded by a halo of quartz-sulphide vein stockwork mineralisation.
Lodes are identified as A through to H, with A, B and C being polymetallic while D to H are copper/gold
dominant.
SOZ lodes primarily occur beneath the Top Shear, a major fault structure within the mine sequence.
Mineralisation has been interpreted using a copper equivalent grade cut-off greater than 1.0%.
www.kingstonresources.com.au
11
Figure 5. Oblique View showing interpreted domains (green – unchanged, red – added and updated, pink – ALode).
Drilling Techniques
The predominant drilling and sampling methods at SOZ have been HQ diamond drilling, RC drilling,
underground sludge (percussion) drilling and face channel sampling. All new and historical drill holes have
been utilised estimating resources except for face samples and sludge holes, which were merely used to
guide geological interpretations.
Table 11: Summary of drilling by drill hole type.
Hole Type
DDH
RC
DDH
Dataset
Total SOZ DDH
Total SOZ RC
KSN and SOZGT (included within Total SOZ DDH)
Count
268
30
26
Metres
46,385
4,886
3,499
Sampling and Sub-Sampling Techniques
Historical core regarded as significantly mineralised was half sawn for sampling. KSN drill core was subsampled by the logging geologist with sampling intervals varying between 30 cm to 1 m.
When sub-sampling RC chips a riffle splitter or conical splitter is typically employed directly off the cyclone.
A portable XRF was used to determine low-grade or background intervals which were spear sampled to
provide 4 m composites for analysis. If anomalous results were subsequently received from the Lab, the
original 1 m bulk sample (stored in green plastic bags) were riffle split and individual 1 m samples were
submitted for analysis.
www.kingstonresources.com.au
12
Sample Analysis Method
Historical samples were analysed for copper, lead, zinc, silver and gold using Aqua Regia. All gold values >5
g/t were then repeated with a 50 g Fire Assay. All pulps returning >1% Cu, >1% Pb, >1% Zn, and/or >25 g/t
Ag were repeated with method Aqua Regia digest (0.5 g) and flame AAS finish.
KSN uses SGS in Townsville for sample preparation and analysis. Samples undergo a 4-acid digest and ICPOES finish with near to total digestion of the sample as possible. Gold analysis is determined by Fire Assay
using lead collection technique, with a 50 g sample charge weight and AAS instrument finish.
Estimation Methodology
The estimation methodology begins by assigning the interpreted geological domains to the assay dataset
and compositing the data to down hole lengths of 1m. Grades are capped by analysing histograms and
probability plots for each metal within each lode (see the table of capping values in the Detailed Estimation
Reports).
The difference between the assays with increasing distance was analysed using variography. Semivariograms were created using normal scores transformation for Au, Ag, Cu, Pb and Zn. Variography was
also completed for arsenic, antimony and sulphur. The resulting parameters were used in the estimation
routines within Micromine software.
Ordinary Kriging (“OK”) was selected for grade estimation of all elements. Grades were estimated into
orthogonal blocks measuring 5m E x 10m N x 5m Z. Sub-blocking down to 1.25m in all directions allowed for
an accurate representation of the lode volumes. The search radius was 50m in the first estimation run and
100m in the second.
Density was estimated using the percentages of the three main sulphide minerals using the following formula.
Density = (Cu%/0.3463 x 4.2 + Pb%/0.8660 x 7.5 + Zn%/0.6709 x 3.75 +
(100 - Cu%/0.3463 - Pb%/0.8660 - Zn%/0.6709) x 2.65)/100
An analysis comparing the theoretical densities to the measured readings and this showed a good correlation
and sufficient confidence in the calculations from the multielement assays. For other areas of the deposit that
did not produce a calculated result, the default density of 2.65 t/m3 was used, based on the dominant host
rock (Tuff).
The grade estimation was validated by comparing estimated grades to sample grades in cross-section,
comparing to previous estimates, and plotting profiles of estimated vs sample grades along the northing and
elevation axes.
Classification Criteria
Blocks have been classified as Measured, Indicated or Inferred based on drill hole spacing, geological
continuity and estimation quality parameters. These criteria were used to determine areas of implied and
assumed geological and grade continuity. Classification was assessed on a per domain basis and resource
categories were stamped onto the individual domains.
The Basis for the Selected Cutoff Grades
The deposit has been reported above a Net Value per tonne (NVPT) of A$50. The NVPT considers the metal
prices, concentrate grade, mining and processing costs, site G & A costs, metallurgical recoveries, payables
and deductions of copper, lead, zinc, gold and silver. NVPT differs from net smelter return (NSR), which is
an often-used metric for polymetallic projects. NSR excludes the on-site costs, such as mining, processing
and site G & A.
www.kingstonresources.com.au
13
Adjusting the NVPT cutoff from an expected A$70/t for mining selection down to A$50/t accommodates for
scenarios where economics could eventually allow for potential mining of lower grade material.
Table 12: Metal prices used within the NVPT formula.
US$
A$
FX
AUD:USD
Gold
$/oz
$ 1,944
$ 2,859
Silver
$/oz
$
24.0
$
35.2
Copper
$/lb
$
4.30
$
6.32
Lead
$/lb
$
0.95
$
1.40
Zinc
$/lb
$
1.19
$
1.75
0.68
Material Modifying Factors Considered to Date
The NVPT formula considers an exhaustive set of modifying factors to assess the potential for eventual
economic extraction. These include metal prices, concentrate grade, mining and processing costs, site G &
A costs, metallurgical recoveries, payables and deductions of copper, lead, zinc, gold and silver. The level of
consideration is now at a level where the type of concentrate product(s) from each lode is considered in
determining if the material can be included in the Mineral Resource.
UNDERGROUND ORE RESERVE ESTIMATION
Ore Reserves Summary
Underground mining is schedule to re-commence in the SOZ orebodies during the second half of calendar
year 2025 (see Figure 2). The maiden SOZ Ore Reserve estimate is based on bottom-up mining by long hole
stoping and uncemented rock fill. Access will be via the existing Eastern Decline with its portal in the Eastern
Ore Zone (EOZ) Pit. The SOZ production rate will be approximately 30,000t per month.
The 30 June 2024 SOZ Ore Reserve Estimate, summarised in Table 2, is for an underground sulphide zone
of an operating project with 350ktpa to 400ktpa flotation capacity and 700ktpa carbon-in-leach (CIL) capacity.
It is based on mine plans prepared using the June 2024 Mineral Hill SOZ Mineral Resource estimate, with
adjustment for depletion of resources from historical mining.
Table 13: Mineral Hill Mine Southern Ore Zone 30 June 2024 Probable Ore Reserves
Estimated Grade
Estimated Contained Metal
Mt
Copper
%
Lead
%
Zinc
%
Gold
g/t
Silver
g/t
Copper
kt
0.7
0.8
1.9
1.6
1.4
20
5.5
Notes:
1.
2.
3.
4.
5.
6.
Lead
kt
13
Zinc
kt
11
Gold
koz
Silver
Moz
30
0.45
The tonnes and grades shown are stated to a number of significant figures reflecting the confidence of the estimate.
For the estimated contained metal:
a. The contained copper estimate is shown to the nearest 0.5kt.
b. The contained gold estimate is shown to the nearest 5koz.
c. The contained silver estimate is shown to the nearest 0.05Moz.
There is no Proved Ore Reserve. The Probable Ore Reserve is derived from Measured and Indicated Mineral Resources.
The Ore Reserve only includes Inferred Mineral Resources as unavoidable dilution within stope shapes, or within
development required