Investor Presentation - RIU Sydney Resources Round-Up
Released
Released
Announcement PDF
Kingston Resources Limited
RIU Sydney Conference Presentation
GOLD AND BASE METAL PRODUCTION
COBAR BASIN, NSW
6-8 MAY 2025
www.kingstonresources.com.au I ASX: KSN
Important notices and disclaimer
Forward Looking Statements
Mineral Hill Gold Bar
Certain statements contained in this presentation, including information as to the future financial or operating performance of KSN and its projects, are
forward looking statements. Such forward looking statements: include, among other things, statements regarding incomplete and uncertain proposals or
targets, production and prices, operating costs and results, capital expenditures, and are or may be based on assumptions and estimates related to future
technical, economic, market, political, social and other conditions; are necessarily based upon a number of estimates and assumptions that, while considered
reasonable by KSN, are inherently subject to significant technical, business, economic, competitive, political and social uncertainties and contingencies; and
involve known and unknown risks and uncertainties that could cause actual events or results to differ materially from estimated or anticipated events or
results reflected in such forward looking statements.
KSN disclaims any intent or obligation to update publicly any forward-looking statements, whether as a result of new information, future events or results or
otherwise. The words “believe”, “expect”, “anticipate”, “indicate”, “contemplate”, “target”, “scope”, “plan”, “intends”, “continue”, “budget”, “estimate”,
“may”, “will”, “schedule” and similar expressions identify forward looking statements. All forward looking statements made in this presentation are qualified
by the foregoing cautionary statements. Recipients are cautioned that forward looking statements are not guarantees of future performance and accordingly
investors are cautioned not to put undue reliance on forward looking statements due to the inherent uncertainty therein.
Disclaimer
No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions and
conclusions contained in this presentation. To the maximum extent permitted by law, none of KSN, its directors, employees or agents, nor any other person
accepts any liability, including, without limitation, any liability arising out of fault of negligence, for any loss arising from the use of the information contained
in this presentation. In particular, no representation or warranty, express or implied is given as to the accuracy, completeness or correctness, likelihood of
achievement or reasonableness or any forecasts, prospects or returns contained in this presentation nor is any obligation assumed to update such
information. Such forecasts, prospects or returns are by their nature subject to significant uncertainties and contingencies.
The information contained in this presentation is for informational purposes only and does not constitute an offer to issue, or arrange to issue, securities or
other financial products. The information contained in this presentation is not investment or financial product advice and is not intended to be used as the
basis for making an investment decision. The presentation has been prepared without taking into account the investment objectives, financial situation or
particular needs of any particular person. Before making an investment decision, you should consider, with or without the assistance of a financial adviser,
whether an investment is appropriate in light of your particular investment needs, objectives and financial circumstances. Past performance is no guarantee
of future performance.
For further information on the Life of Mine at Mineral Hill referred to in this Presentation, refer to the Company’s ASX Announcement dated 27 June 2023 and
30 September 2024
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
2
Important notices and disclaimer
Exploration by Other Explorers
This presentation contains information sourced from the reports of other Explorers. References to the original reports are provided as footnotes where the information is cited in this
presentation. KSN does not vouch for the accuracy of these reports. KSN has taken the decision to include this information as it is in the public domain and as we assess it to be of relevance to
shareholders and investors.
Production Target
The LOM plan includes Mineral Resource Estimates for Pearse pits, the Southern Ore
Zone (SOZ) and Jack’s Hut to estimate the Production Target1. All Ore Reserves and
Mineral Resources underpinning this LOM plan have been prepared by Competent
Persons in accordance with the 2012 JORC reporting guidelines. The Production
Target comprises 51% Ore Reserves, 11% Measured & Indicated Resources and 38%
Inferred Resources. The first 12 and 36 months of the Production Target are
underpinned by 89% and 80% of Measured and Indicated Resources respectively
There is a low level of confidence associated with Inferred Mineral Resources and
there is no certainty that further exploration work will result in the determination of
Indicated Mineral Resources or that the production target itself will be realised.
The stated production target is based on the Company’s current expectations of
future results or events and should not be solely relied upon by investors when
making investment decisions. Further evaluation work and appropriate studies are
required to establish sufficient confidence that this target will be met. The Company
notes that the Project forecasts a positive financial performance and is therefore
satisfied that the use of Inferred resources in production target reporting and forecast
financial information is not the determining factor in overall Project viability and that
it is reasonable to report the LOM plan with Inferred Resources.
The Company has concluded that it is has a reasonable basis for providing the
forward-looking statements included in this announcement. The detailed reasons for
that conclusion are outline throughout this presentation.
1. See ASX Announcement dated 27 June 2023, 2 April 2024 and 30 Sept 2024, for further detail and key assumptions
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
3
Kingston Resources: Investment highlights
Gold production at spot price: Kingston is producing
gold and silver from open pit mining.
Mineral Hill processing plant: Operating at full capacity,
weekly gold/silver dore sales. Copper1 production from
underground in FY26
Expansion: Exploring for new deposits, expanding the
mine plan through exploration and acquisition.
Strategic assets and infrastucture: Growth options in
Cobar Basin, material value in Misima with the current
gold market.
1. See ASX Announcement dated 27 June 2023, 2 April 2024 and 30 Sept 2024, for further detail and key assumptions
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
4
Corporate snapshot
Shares on issue
1-Year Share Price Performance
Warrants & options2,3
168.4m
Share price (17/3/2025)
$0.09
Market cap
$74m
Cash @ 31 March 20251
Market Volume('000) RHS
821m
Close Price (A$) (LHS)
0.12
0.1
0.08
0.06
0.04
0.02
0
40,000
30,000
20,000
10,000
0
$12.48m
Restricted cash for environmental bond
$7.4m
Debt4
$15m
Shareholder Structure
Delphi 14.5%
Quintana 8.1%
Winchester 7.9%
Farjoy 7.4%
Other 62%
1. Estimated Cash balance, as at 31 Mar 2025, excludes $7.4m cash backed environmental bond.
2. 38m unlisted options @ $0.14, exp 31 July 25.
3. 25m unlisted warrants @ $0.0816, exp 07 July 2027, 35.7m unlisted warrants @ $0.0816 exp 29 June 2028, 69.7m warrants @
$0.0879, exp 23 Feb 2028.
4. Debt payback - $5m matures 7 July 2026, $5m matures 23 February 2027,$5m matures 29 June 2027,
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
5
Mineral Hill
Gold and Copper Mine
Pearse North Open Pit
April 2025
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
6
Kingston’s Key Achievements at Mineral Hill
Growth platform to build a mid-tier gold and copper producer
Operating Cash
Flow
• Material cash flow
from tailings mining
and open pit mining
• Open pit mining fully
ramped up
www.kingstonresources.com.au I ASX: KSN
Processing Plant
Underground
• Refurbishment of
crushing, grinding
and flotation circuits
• Building tailings
storage capacity
• Pumping
• Ground support
rehabilitation
• Surface &
Underground drilling
• Maiden Ore Reserve
Community
Engagement
• 52% of the workforce
sourced locally
• Supporting local
businesses by
purchasing within the
region
Corporate Presentation | May 2025
7
The Mineral Hill story so far
Transformative return on investment and growth
• Mineral Hill was purchased in
Jan 2022 for $23 million2
• Revenue to date $137 million1
Production
and Cash
Flow1
42koz
$137m
Gold sales
$38m
Operating
margin
Net revenue
• Operating cash flow to date
$38 million1
• Full approved and operating
• Six-year mine life with multiple
targets to extend
Contribution
to the Local
Economy
$14m
Employment
Growth
197%
$31m
Plant refurb
Condobolin
region
expenditure
$34m
NSW based
expenditure
• Investing in the asset to
expand
• Investing in local people
• Investing in the local
businesses and community
www.kingstonresources.com.au I ASX: KSN
1.
2.
Employment
growth since
Jan 2022
Reporting period from Jan 2022 to Mar 2025
See ASX announcement 18/1/2022
16%
7%
Female
employment
Indigenous
employment
Corporate Presentation | May 2025
8
Mining schedule
Open pit mining and processing to Q4FY25
Life of mine out to 2031 – 6 years
• Transitioning to
flotation processing
Pearse South
• Mining inventory:
191kt @ 3.3g/t gold
and 69g/t silver
• Currently waste
stripping
www.kingstonresources.com.au I ASX: KSN
Dec-27
Jun-27
Dec-26
Jun-26
Dec-25
Jun-25
• Mining inventory:
217kt @ 2.2g/t gold
and 25g/t silver
remaining*
Dec-24
Pearse North
Open Pit
Mining
Open Pit
Processing
UG Mining
UG Processing
* Reporting from 1 April 2025. Refer to ASX announcement on 30/9/2024
Corporate Presentation | May 2025
9
Open Pit Mining – Pearse North
Successful production, processing and financial performance1
March 2025 quarterly highlights1:
Summary
Unit
Q1 FY25
Q2 FY25
Q3 FY25
Revenue
A$m
N/A2
14.0
19.7
Operating Cash Flow
A$m
N/A2
6.4
5.4
Waste Mined
T
413,600
654,080
557,351
Ore Processed
T
43,269
73,717
89,051
Head Grade
g/t
1.51
1.56
1.84
Processing Recovery
%
89%
89%
76%
Gold Sales
Oz
1,680
3,261
3,960
Silver Sales
Oz
11,551
22,862
22,021
AISC
A$/oz
N/A2
2,814
2,851
Average Gold Price
A$/oz
3,777
4,101
4,591
Gold and silver dore from open pit production at Mineral Hill
1. See March Quarterly Activities Report – ASX Announcement dated 28 April 2025
2. $6.2m of Pearse revenue capitalised. Commercial production for Pearse was declared in Q2FY25
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
10
Underground early works underway
Two existing underground mines with declines and
ventilation systems in place
Setting up the long-term future of Mineral Hill
• Underground mine life >5-years
• Leveraging existing infrastructure & approvals.
• UG development due to commence early 2026
• Copper production in mid 2026
• 85% of forecasted revenue from copper & gold production1
Southern Ore Zone Underground Mineral Resources2
Class
Tonnes
kt
Cu
%
Pb
%
Zn
%
Au
g/t
Ag
g/t
Cu
kt
Pb
kt
Zn
kt
Au
koz
Ag
koz
Total
3,776 1.0
1.3
1.1
1.83
17 37
51
40
222 2,038
Southern Ore Zone Underground Ore Reserve1
Class
Tonnes
kt
Cu
%
Pb
%
Zn
%
Au
g/t
Ag
g/t
Cu
kt
Pb
kt
Zn
kt
Au
koz
Ag
koz
Probable
700 0.8
1.9
1.6
1.4
20 5.5
13
11
30
450
Long-hole open stopes
Oblique view of the Southern Ore Zone planned stopes
1. See ASX Announcement dated 30 September 2024,
2. Due to rounding to appropriate significant figures, minor discrepancies may occur, tonnages are dry metric tonnes.
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
11
SOZ Underground – Drilling Program
Expanding Resources and extending operational life of mine
• Underground diamond drilling: commenced in Feb 2025.
• Focus: Infill & extension of existing resources, targeting both stope
shapes and high-grade lodes.
• Significant resource expansion potential: Targeting depths from
450m down to 1.8km, aligning with typical Cobar-style deposits.
Mineral Hill
www.kingstonresources.com.au I ASX: KSN
SOZ Underground diamond drilling
Peak
Corporate Presentation | May 2025
12
Increase scale at Mineral Hill
Strategy on expanding Mineral Resources and making new discoveries
EOZ high
grade Au
target
Currently 7.2Mt of
underground resources
GD140
target
Parkers Hill
MRE update and
extensions
Plan:
• Underground drilling
Red Terror
target
• Update Resource
estimates
• Add other brownfields
deposits to the mine plan
(currently SOZ only)
SOZ MRE1
update
Jacks Hut
Infill & Extension
Key resource expansion projects:
• SOZ infill & extension drilling.
• Parkers Hill resource update.
• Jacks Hut and EOZ extensions.
12.5m @
3.41% CuEq
G-H Lode Infill
1. MRE – Mineral Resource Estimate
2. See ASX Announcement dated 21 March 2023 and 30 September 2024 for MRE announcements
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
13
Extension potential at depth and regionally
Mineral Hill remains open at depth and along the regional trends
• Depth of drilling
<500m depth
• Major mineral
deposits in Cobar
extend to ~1.8km
• Numerous
regional
exploration
targets
(long section looking SW)
13km
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
14
Grow the operating scale with regional exploration
Highly prospective drill targets and geochemical signatures
• Major capital investment complete
• Open pit mining underway
• Underground mining in 2026
• Generating cash flow
• Focus on value-driven exploration:
• EL8334: High-potential targets
• Strong soil & geophysical results
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
15
Add projects within trucking distance to Mineral Hill
Mineral Hill is the only processing facility in the southern Cobar Basin
Grow resources and expand daily throughput
2,000
t/day
tpd
2,000
1,000
t/day
tpd
1,000
Today – 360,000 tpa
Target a
doubling of
production
Target – 700,000 tpa
Resource growth strategy
Mineral Hill
Extensions
Regional
Acquisition
Increase
grinding &
flotation
capacity
Regional Exploration
EL8334
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
16
Misima Gold Mine – circa 1995
Misima
Gold Project
Corporate Presentation | May 2025
17
Misima – high value growth asset
Large scale, long-life, low-cost open pit gold and silver mine
• Large, low-cost, 20-year gold project averaging
128koz gold per annum
• Base case NPV of A$956m1 at a gold price
US$1,800/oz
• Gold price scenario of $2,700/oz lifts NPV to $2.7bn
• Formal process being managed by Argonaut to bring
about value realisation
SIMBERI
6
PNG Mines and Projects
Estimated Gold Endowment
AuEq Moz
66
LIHIR
17 FRIEDA RIVER
24
17 OK TEDI
Unit
Base
Spot
Gold Price
USD/oz
US$1,800/oz
US$2,700/oz
Exchange Rate
AUD:USD
US$0.70
US$0.66
LOM Revenue
A$m
6,116
9,730
LOM Free Cash Flow (pre-tax)
A$m
2,726
6,367
NPV (7% real) pre-tax
A$m
956
2,696
NPV (7% real) post-tax
A$m
624
1,859
IRR pre-tax
%
22%
46%
IRR post-tax
%
18%
37%
23 PANGUNA
KAINANTU
2
PORGERA
Item
DFS Highlights
27
WOODLARK
WAFI-GOLPU
HIDDEN VALLEY
4
Papua
New Guinea
TOLUKUMA
2
PORT
MORESBY
2
1.6
7
Misima
GOLD RIDGE
2.4Moz
128koz pa
$2.7bn
20-year
LOM gold
production
average gold
production
(yrs 2-18)
pre-tax FCF
mine life –
production target
1. See KSN ASX announcements on 6 June 2022 for further detail
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
18
KSN offers leverage to a rising gold price
5
4
3
High leverage to the gold price
Gold Price USD per ounce
2
2021
1
2019 – KSN
2017 - KSN
completes
100%
ownership
Resource
grows to
3.8Moz
commences
Misima earn-in
$3,000
2022
Misima
DFS
KSN initiates
sale/JV
process
Today we are selling
gold at over USD
$3000/oz
$2,500
5
$2,000
1988
Commencement of
mining
$1,500
2004
Misima
decommissioned by
Placer Dome
3 4
2
1
Placer Dome Mining Period
4.0Moz AuEq over 15 years
$1,000
$500
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
$0
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
19
Summary: Focus on executing our clearly defined strategy
Leveraging the existing gold-copper asset base while advancing future growth opportunities
Experienced Management Team: Focus on maximising
returns from Mineral Hill and Misima
Prime Cobar Location: Mineral Hill in the Cobar Basin, rich in
copper & gold (clean energy transition),
Fast-Track Production Boost: Expanding cashflow and
production from open pit mining and moving into
underground mining
Strategic Advantage: Fully approved and operating
processing plant with multiple drill targets and growth
options
Misima Gold Project: Large scale, long-life, low-cost open
pit gold and silver project
SOZ Underground Mine
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
20
Appendix
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
21
Highly experienced and well-regarded Executive Team
Significant experience across the development life cycle through to production
Mick Wilkes
Andrew Corbett
Tony Wehby
Stuart Rechner
Non-Executive Chairman
Managing Director
Non-Executive Director
Non-Executive Director
Mick is a seasoned mining
professional with 35 years’
experience in the industry,
primarily in gold and base
metals. He has specialised in
sustainable project
development, construction, and
operations throughout his
career.
Andrew is a highly experienced
mining engineer with over 25
years in mine management and
financial markets. He has an indepth understanding of mining,
equity markets, business
development and corporate
strategy.
Tony is a highly experienced
board member and chairman,
previously Non-Executive
Chairman of Tellus Resources
Limited and Aurelia Metals
Limited, and a Director of
Ensurance Ltd.
Stuart is an experienced
company director and geologist
with a background in project
generation and acquisition in
Australia and overseas. Mr
Rechner holds degrees in both
geology and law.
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
22
Building a safe and
sustainable culture
Investing in our people and
our community
A large employer in
Condobolin
ESG framework: safe,
responsible and sustainable
Investing in our local and
residential workforce
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
23
Mineral Hill – Social License
Environmental and Social Licence to operate
Permits in place for mining and processing
Cash backed environmental bonds
Tailings capacity in place and expansion plans
scheduled
Biodiversity offset established
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
24
Competent Person Statement
Competent Person’sStatement - Mineral Resource Reported in Accordance with 2012 JORC Code – Mineral Hill
The information in this report that relates to the reporting of the Mineral Hill Mine Mineral Resource Estimate is based on and fairly represents,
information and supporting documentation compiled by Mr. Stuart Hayward (BAppSc (Geology)) MAIG ,who is a Member of the Australian
Institute of Geoscientists. Mr. Stuart Hayward is a full-time employee of Kingston Resources Limited. Mr. Hayward has sufficient experience
relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’. Mr. Hayward confirms that the information in the market announcement provided is an accurate representation of the available data
and studies for the material mining project and consents to the inclusion in this report of the matters based upon the information in the form and
context in which it appears. The Company confirms that the form and context in which the Competent Person’s findings are presented have not
been materially modified from the original report.
Competent Person’sStatement - Mineral Resource Reported in Accordance with 2004 JORC Code – Mineral Hill
Competent Person’sStatement - Mineral Resource Reported in Accordance with 2012 JORC Code – Misima
The information in this report that relates to the reporting of the Misima Mineral Resource Estimate is based on and fairly represents, information
and supporting documentation compiled by Mr. Stuart Hayward (BAppSc (Geology)) MAIG ,who is a Member of the Australian Institute of
Geoscientists. Mr. Stuart Hayward is a full-time employee of Kingston Resources Limited. Mr. Hayward has sufficient experience relevant to the
style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as
defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr. Hayward
confirms that the information in the market announcement provided is an accurate representation of the available data and studies for the
material mining project and consents to the inclusion in this report of the matters based upon the information in the form and context in which it
appears. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially
modified from the original report.
The information in this release that relates to Mineral Resources is based on information reviewed by Mr. Stuart Hayward (BAppSc (Geology))
MAIG, who is a Member of The Australian Institute of Geoscientists and a full-time employee of Kingston Resources Limited. Mr Hayward has
sufficient experience in the style of mineralisation and types of deposit under consideration and to the activity he is undertaking to qualify as a
Competent Person as defined in the 2004 Edition of the ‘Australian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’. Mr. Hayward confirms that the information in the market announcement provided is an accurate representation of the available data
and studies for the material mining project and consents to the inclusion in the report of the matters based on his information in the form and
context in which it appears. All Mineral Resource estimates were prepared and first disclosed under the JORC Code 2004 and are an accurate
representation of the available data and studies for the Mineral Hill Mine. This information has not been updated since to comply with the JORC
Code 2012 on the basis that the information has not materially changed since it was last reported. Work will commence on close of acquisition by
the Company to bring each of the Mineral Resourcesinto line with the JORC Code 2012.
Competent Person’sStatement – Ore Reserve Reported in Accordance with 2012 JORC Code – Misima
Competent Person’sStatement – Ore Reserve Reported in Accordance with JORC Code – Mineral Hill
Deposit
JORC
ASX Announcement
Competent Person
Company
The Ore Reserve and Mineral Resources estimates were prepared by a Competent person in accordance with the JORC Code 2012 with
exception of the Parkers Hill Mineral Resource Estimates that have been prepared by a Competent Person in accordance with the JORC Code
2004 and have not been updated to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was
last reported. Pearse, Parkers Hill, Jacks Hut and the Southern Ore Zone Mineral Resource estimates and Ore Reserves have been adjusted by
mining depletion using the production wireframes created by the site survey department at the time of mining. These wireframes represent the
mining activities at these deposits to the best of Kingston’s knowledge although they are not to be viewed as complete or accurate in their
entirety and therefore mining depletion may be revised when Kingston is able to produce revised determinations on more complete data and
verification thereof. Information pertaining to Mineral Resource Estimates (MRE) and Ore Reserves (OR) in this presentation has been previously
released to the public. The tables on this page indicate the authors of the historical Resources/Reserves and the dates they were initially
published. Kingston is not reporting these estimates as its own with exception of the MRE and OR for the TSF which has not been reported
previously by any other company. The other original reports are available through the ASX website.
Misima
2012
KSN 06/06/2022
John Wyche
AMDAD
Pearse North
2012
KSN 30/9/2024
John Wyche
AMDAD
Pearse South
2012
KSN 30/9/2024
John Wyche
AMDAD
SOZ
2012
KSN 30/9/2024
John Wyche
AMDAD
Deposit
JORC
ASX Announcement
Competent Person
Company
The Competent Person signing off on the the overall Pearse Opencut Ore Reserves Estimate is Mr John Wyche BE (Min Hon) BComm CP, of
Australian Mine Design and Development Pty Ltd, who is a Fellow of the AusIMM and who has sufficient relevant experience in operations and
consulting for open pit metalliferous mines. Mr Wyche consents to the inclusion in this report of the information pertaining Mineral Hill Pearse
open pit Ore Reserves in the form and context in which it appears.
Misima
2012
KSN 15/09/2021
Stuart Hayward
KSN
Pearse South
2012
KSN 15/03/2023
Stuart Hayward
KSN
Pearse North
2012
KSN 7/05/2024
Stuart Hayward
KSN
The Competent Person signing off on the overall underground SOZ Ore Reserves Estimate is Mr Steven Weckert BE ME (Min) CP, of Australian
Mine Design and Development Pty Ltd, who is a Member of the AusIMM and who has sufficient relevant experience in operations and
consulting for underground metalliferous mines. Mr Weckert consents to the inclusion in this report of the information pertaining to the Mineral
Hill SOZ Ore Reserve in the form and context in which it appears.
Southern Ore Zone
2012
KSN 30/09/2024
Stuart Hayward
KSN
Jack’s Hut
2012
KSN 21/03/2023
Stuart Hayward
KSN
Parkers Hill
2004
KBL 13/09/2011
Anthony Johnston
KBL
www.kingstonresources.com.au I ASX: KSN
The Competent Person signing off on the overall Misima Ore Reserves Estimate is Mr John Wyche BE (Min Hon), of Australian Mine Design and
Development Pty Ltd, who is a Fellow of the Australasian Institute of Mining and Metallurgy and who has sufficient relevant experience in
operations and consulting for open pit metalliferous mines. Mr Wyche consents to the inclusion in this report of the matters based upon the
information in the form and context in which it appears.
Kingston confirms that it is not aware of any new information or data that materially affects the information included in all ASX announcements
referenced in this release, and that all material assumptions and technical parameters underpinning the estimates in these announcements
continue to apply and have not materially changed.
Ore Reserve
Mineral Resource
Corporate Presentation | May 2025
25
Metal equivalents
This presentation quotes metal equivalent grades for the life of mine plan, Mineral Resources and Ore Reserves. Price assumptions used are based primarily on
consensus forecasts with adjustments based on company expectations. Gold equivalent (AuEq) and copper equivalent (CuEq) conversion factors are used
within the announcement and are calculated by dividing price/unit for each commodity (Cu/t, Au/oz, Ag/oz, Pb/t, Zn/t) and multiplying by the metallurgical
recovery. Since the metallurgical recovery varies according to deposit type, the metal equivalent factors are unique for each deposit (I.e. Tailings Project, Open
Pit, and Underground).
Metallurgical recoveries are based on historical production (2010-2016) as well as recent metallurgical test work and are applied to the Resource and Reserve
calculated grades for each commodity. The Company is of the opinion that all the elements included in the metal equivalent calculations have a demonstrated
potential to be recovered and sold. Mineral Hill has a CIL circuit, Cu flotation circuit, Pb flotation circuit and Zn flotation circuit to produce three different
concentrates as well as gold dore.
AuEq g/t = (128.46 * Cu %) + (0.76 * Au g/t) + (0.01* Ag g/t) + (35.06 * Pb %) + (31.98 * Zn %)
Commodity
Unit
Price
Deposit
Commodity
Recovery (%)
AuEq Factor ()
Gold
US$/oz
2,236
Open Pit
Gold
75
0.75
Silver
US$/oz
27.6
Silver
69
0.01
Copper
US$/lb
4.95
Underground Gold
60
0.76
Lead
US$/lb
1.09
Silver
79
0.01
Zinc
US$/lb
1.37
Copper
88
122.75
Lead
75
26.54
Zinc
66
25.30
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
26
Misima Gold Project – Resources & Reserves
Misima Resources & Reserves
Indicated Resource Inventory
Misima Resources Total
Au
Ag
C/O
Au
Ag
(Moz)
(Moz)
Deposit
Ag
Mt
(g/t)
(g/t)
C/O
Au
Ag
(Moz)
(Moz)
Deposit
Mt
(g/t)
(g/t)
Umuna
93.5
0.78
4.3
0.3
2.4
13.1
Umuna
157.6
0.7
4.1
0.3
3.6
20.5
Ewatinona
4.2
0.88
2.6
0.3
0.12
0.3
Ewatinona
7.6
0.81
2.8
0.3
0.2
0.7
Cooktown
Stockpile
-
-
-
-
-
-
Cooktown
Stockpile
3.8
0.65
7
0.5
0.1
0.9
TOTAL
97.7
0.