Quarterly Activities Report
Released
Released
Announcement PDF
QUARTERLY REPORT
30 April 2024
ABOUT KINGSTON
RESOURCES
Kingston Resources is a gold
producer, focused on building
a mid-tier gold and base
metals company, with current
production from the Mineral
Hill gold and copper mine in
NSW, and advancing its
flagship development asset,
the 3.8Moz Misima Gold
Project in PNG.
QUARTERLY ACTIVITIES REPORT
For the period ending 31 March 2024
HIGHLIGHTS
Mineral Hill Gold & Copper Mine, NSW
•
o
Gold sold 3,026oz
o
Average gold price A$3,165/oz
o
AISC of A$2,597/oz
CAPITAL STRUCTURE
o
A$9.68M in sales and A$1.67m in operating cash flow
Shares on Issue: 633.7M
Market Cap: A$45M
Cash:(8 April 2024) A$10.7m
o
February production was impacted by lower gold recoveries
•
DIRECTORS &
MANAGEMENT
Mick Wilkes
Non-Executive Chairman
Andrew Corbett
Managing Director & CEO
Stuart Rechner
Non-Executive Director
Tony Wehby
Non-Executive Director
Stuart Hayward
Chief Geologist
Geoff Merrell
GM, Mineral Hill
•
ASX: KSN
See ASX Announcement on 6
www.kingstonresources.com.au
o
Confirmation of the newly discovered underground lode at the Southern
Ore Zone (SOZ).
o
SOZ infill drilling has confirmed high-grade mineralisation over 400m
strike.
Process plant refurbishment:
o
Final work programs are nearing completion with initial oxide open pit ore
from Pearse to be fed at the end of the June quarter.
o
Major work included structural refurbishment of the crushing circuit and
fine ore bins, delivery of new electrical circuitry units and installation of
new conveyor components.
•
Recent momentum in the gold price has spurred significant interest in
Misima. Discussions are continuing with numerous interested parties in
relation to potential partnerships and development pathways.
•
Misima is highly leveraged to the gold price, with a US$2,400/oz gold price
and 0.65 AUD:USD FX scenario forecast to deliver a $2.2bn NPV1 pre-tax.
www.kingstonresources.com.au
ABN: 11 060 156 452
E:info@kingstonresources.co
m.au
A: 202/ 201 Miller Street,
North Sydney, NSW
2060
Share Register:
LinkedIn: Kingston Resources
Limited
Twitter: @KSNResources
Exploration:
Misima Gold Project, PNG
CORPORATE DETAILS
1
March Quarter production from the Tailings Project:
Corporate
•
Placement and Entitlement Offer to raise $13.5m. The $4.5m retail
component of the Entitlement Offer closes on the 8th May and is fully
underwritten. Proceeds to be used towards transitioning to Pearse open pit
mining, underground resource drilling and processing plant commissioning.
•
Cash balance at 31 March 2024 $4.09M.
June 2022
1
Kingston Managing Director, Andrew Corbett, said:
"We are very pleased with the production success we’ve had so far from the tailings retreatment project. The
financial returns have allowed us to invest significantly in foundational infrastructure such as tailings storage
facilities and refurbishment of the process plant and underground development. We have set the company up
for a long term operation.
Pearse North and South open pits are both high grade gold-silver projects. We are taking advantage of the
recent strong rally in the gold price by shifting gears to accelerate gold production from these high margin open
pits.
Our recent exploration success in the underground resource areas is highly encouraging. The near mine
discovery at the Southern Ore Zone is showing that this mineral system has a lot of growth potential. Mineral
Hill’s life of mine is predominantly comprised of underground polymetallic Mineral Resources and we are
working towards expanding the mineral inventory to sustain a long-term operation. We will be back in the
underground development in the September quarter to do additional infill and extension drilling.
The recent placement and entitlement offer will unlock the next level of cash flow generation with the Pearse
open pits. The crushing, grinding and flotation circuits are close to the commissioning phase and we’ll be
commencing the initial strip on Pearse North in the June quarter.
A polymetallic processing plant that can produce three concentrates and precious metal dore is a major
strategic advantage for the company. The plant is one of two in the Cobar Basin that has this type of capability.
We want to look further into the potential for expanding processing capacity in the medium term to increase
scale and maximise cash flow. The whole region has historically been under explored and so we see an
opportunity to prioritise our operating cash flow towards exploration, make additional discoveries and increase
the likelihood of a plant expansion.
We have built strong local operating expertise from our Tailings Project and we are now leveraging that
knowledge to our next phase of open pit mining. We’re very pleased to play the role we do in increasing
prosperity for our local region." - Managing Director, Kingston Resources
www.kingstonresources.com.au
2
MINERAL HILL MINE
Exploration
Exploration work remained focused on the underground resources at the Southern Ore Zone (SOZ). In
particular, drilling programs aimed at increasing the confidence in the current Mineral Resource estimates
and exploring for extensions to the mineralisation. Infill and extensional drilling into the Southern Ore Zone
returned high grade polymetallic assays and resulted in the confirmation of the near mine discovery made in
the December quarter of 2023.
Figure 1: Mineral Hill regional geology, resources and infrastructure.
Near-Mine Underground Discovery
Kingston made a second intersection into the newly discovered underground lode during the quarter. Drill
hole KSNDDH019 followed up the initial intersection made in KSNDDH017 in the footwall of the Southern
Ore Zone (See ASX announcement on 15 February 2024). Significant assays over this zone include:
•
12.5m @ 3.41% CuEq from 405m (KSNDDH017)
•
2m @ 6.37% CuEq from 255m (KSNDDH019)
These two drill holes have also confirmed the historical significant intercepts from “New Structure #1” and
highlighted the potential to extend the mineral resources at depth.
www.kingstonresources.com.au
3
Existing
Mineral
Resource
Zone
Potential
Mineral
Resource
Expansion
Zone
Figure 2: Cross Section showing new structures intersected outside existing Mineral Resource
The confirmation of the new lode marks a significant milestone for the company, as it paves the way for
further discoveries within the mine. The Southern Ore Zone remains open along strike at both ends and at
depth. The availability of suitable drilling platforms has been the only limiting factor for continuing to expand
the footprint of underground mineralisation so far. This will be resolved in the near future as underground
refurbishment continues.
www.kingstonresources.com.au
4
Confirmation of the Main Underground Lode over 400m.
Additional infill and extensional drilling into the underground resources was undertaken during the March
quarter. Outstanding assay results were reported after the end of the quarter, clearly illustrating the highgrade nature of the deposit and the region’s metal endowment (see ASX announcement on 9 April 2024).
Drill holes KSNDDH020, 21, 22 and 23 were drilled to infill the upper areas of the underground resources
and aimed at increasing the confidence and extent of the existing resources. The main lode in this part of the
deposit (namely, the A-lode) has now been traced continuously over 400m strike and 200-250m down dip.
Significant intersections include:
•
9m @ 3.14% CuEq from 214m (KSNDDH020):
o
•
4m @ 2.38% CuEq from 228m (KSNDDH020)
o
•
Including 3m @ 8.13% CuEq
Including 3m @ 4.67% CuEq from 191m (KSNDDH021)
7.0m @ 3.76% CuEq from 164m (KSNDDH022):
o
Including 3m @ 6.18% CuEq from 165m
•
8.0m @ 2.06% CuEq from 173m (KSNDDH023)
•
10.2m @ 2.73% CuEq from 187.8m (KSNDDH023)
Figure 3: Drill core from KSNDDH021 (4m wide sulphide rich breccia lode (estimated true width of 2m) within a broader 31.6m wide brecciated
and veined lode zone from 175.3mdh).
www.kingstonresources.com.au
5
Figure 4: Plan view of recent drill holes and mineralisation at SOZ..
Additional extension and infill drilling into the underground resources is due to commence early in the
December quarter of 2024. The principal aims of further drilling remain focused on extending the life of mine
and improving confidence in the current estimates.
Operations
Kingston completed the quarter with 1,308oz produced in March. Significant operating challenges were
experienced in February owing to elevated base metal grades, which negatively impacted gold recoveries in
the CIL processing circuit. The company acted quickly at the start of March to move to a higher-grade section
of the dam with less base metal contamination and increased tonnage throughput. The Tailings Project has
been a highly successful operation for Kingston, delivering $25.29M of operating cash flow since acquiring
the project in January 2022 to 31 March 2024.
www.kingstonresources.com.au
6
Table 1: March 2024 quarter production summary.
December Quarter
March Quarter
Q on Q change
136,531
150,164
10.0%
Average Feed Grade (g/t)
1.34
1.13
-16.3%
Processing Recovery (%)
58%
55%
-4.9%
Gold Production (oz)
3,409
2,984
-12.5%
Gold Sales (oz)
3,627
3,026
-16.6%
Silver Sales (oz)
5,685
3,813
-32.9%
AISC (A$/oz)
$2,302
$2,597
12.8%
Realised Gold Price (A$/oz)
$3,041
$3,165
4.1%
Sales (A$m)
$11.20
$9.68
-13.6%
Operating Cashflow (A$m)
$2.64
$1.67
-36.8%
Tonnes Processed (t)
Gold Sold (oz)
AISC (A$/oz)
Realised Gold Price (A$/oz)
2,000
4,000
1,800
3,500
3,326
3,092
3,067
3,000
Gold Sales (oz)
1,400
1,200
2,500
2,342
2,285
1,000
2,000
800
1,500
600
1,000
Gold Price and AISC (A$/oz)
1,600
3,578
400
500
200
0
0
Jan-23
Feb-23
Mar-23
Figure 5: Monthly gold sold, AISC and realised gold price.
The operating strategy at Mineral Hill is to extract the highest grade material remaining in the Tailings Project
and simultaneously accelerate the preparatory work for transitioning to open pit mining at Pearse. The
forecast for the two pits is expected increase in gold and silver output substantially. Total open pit production
is forecast to be 258kt @ 3.72g/t gold and 57g/t silver (at A$2571/oz price and AISC A$1,339)2. Mining is
scheduled to commence in June 2024 and will be completed over an 11-month period. With the recent
movements in the gold price, the pits will be re-optimised using higher gold prices in order to ensure the
greatest value is extracted from these assets. The company will be updating the market at the completion of
this work.
2
See ASX Announcement dated 27 June 2023, $6.5m Capital Raising or Mineral Hill Production Expansion for key
assumptions.
www.kingstonresources.com.au
7
Processing Plant Refurbishment and Commissioning
The refurbishment of the processing plant at Mineral Hill is now in the final stages. All major equipment has
been ordered, allowing the company to directly control adherence to budget. With a forecast annual
production of ~7.0ktpa CuEq and a refurbishment budget of $12.5m, the project has a very low capital
intensity for recommencing hard rock mining.
The main work completed during the quarter includes major structural refurbishment of the crushing circuit
and fine ore bins, delivery of two new motor control centre units for crushing and grinding electrical circuitry
and installation of new converor components. All major long lead items have been ordered, with most of the
deliveries already made and final components expected in the June quarter. Commissioning of the crushing
circuit is due to commence in April.
Figure 6: Refurbished conveyor belts at the comminution circuit (left) and the refurbished fine ore bins (right).
www.kingstonresources.com.au
8
MISIMA GOLD PROJECT
The Misima Gold Project is a long-life, high margin gold project that is highly leveraged to the gold price.
Recent momentum in the spot gold price is highlighting the potential for a significant positive impact on the
financial forecasts. From sensitivity analysis undertaken in the DFS3, a gold price of US$2,400/oz and
AUD:USD exchange rate of 0.65 is forecast to deliver an NPV of approximately A$2.2bn pre-tax.
Figure 7: Misima Island location.
The company has received numerous inquiries from interested parties looking to partner on the project.
Misima has a long and successful history of mining and Kingston is squarely focused on delivering the
greatest value for the project. Discussion continues to prioritise bringing the project into production and
building substantial cash flows into the future.
Table 2: DFS Production Target Summary and Economics and Net Present Value sensitivities
NPV Sensitivity
AUD:USD
3
US$/oz Gold Price
1,500
1,600
1,700
1,800
1,900
2,000
2,100
2,200
2,300
2,400
0.55
1,154
1,355
1,557
1,759
1,960
2,162
2,364
2,566
2,767
2,969
0.60
892
1,077
1,261
1,446
1,631
1,816
2,001
2,186
2,371
2,556
0.65
670
841
1,011
1,182
1,353
1,523
1,694
1,865
2,036
2,206
0.70
480
639
797
956
1,114
1,273
1,431
1,590
1,748
1,907
0.75
315
463
611
759
907
1,055
1,203
1,351
1,499
1,647
0.80
171
310
449
587
726
865
1,003
1,142
1,281
1,420
0.85
44
175
305
436
566
697
827
958
1,088
1,219
0.90
(69)
55
178
301
424
548
671
794
917
1,041
0.95
(170)
(53)
64
181
297
414
531
648
764
881
1.00
(261)
(150)
(39)
72
183
294
405
516
627
738
See ASX Announcement on 6 June 2022
www.kingstonresources.com.au
9
CORPORATE
Kingston completed the institutional component of a $13.5 million capital raising after the completion of the
March quarter. The institutional component raised a total of approximately $8.8 million through a $8.1 million
private placement ("Placement") and a $730k accelerated institutional component of the entitlement offer. A
further $4.7 million is to be raised under the Retail component of the Entitlement Offer. The retail component
of the Entitlement Offer is fully underwritten by Deutsche Balaton Aktiengesellschaft, an associate of Delphi
Unternehmensberatung Akteingesellschaft, an existing shareholder and a sophisticated investor.
Proceeds raised through the Placement and Entitlement Offer will be used to transition to Pearse open pit
mining, underground resource development drilling, processing plant commissioning and general working
capital.
The Company’s closing cash balance at 31 March 2024 was $4.09 million in unrestricted cash and a further
$7.2 million in restricted cash (environmental bonds). The consolidated group cash flow for the quarter is
summarised below:
Net cash from/(used in)
Gross revenue ($m)
9.587
Production cost ($m)
(5.447)
Staff cost ($m)
(2.055)
Administration and corporate cost ($m)
(0.270)
Net interest payment ($m)
(0.263)
Net cash flow from operating activities($m)
1.552
Exploration and development expenditure ($m)
(0.829)
Net cash flow from investing activities ($m)
(7.626)
Net cash flow from financing activity ($m)
(0.259)
During the quarter, the Company made payments totaling $172,000 to associates or related parties reflecting
fees, wages, and superannuation paid to Directors.
www.kingstonresources.com.au
10
Table 3: Tenement Schedule (ASX LR 5.3.3) as at end of quarter
Tenement
Project Name & Location
Status
Ownership
Type
Title Area
EL1747
Misima, PNG
Live
100%
EL
180 km2
EL1999
Mineral Hill, NSW
Live
100%
EL
17 UNITS
EL8334
ML5240
Mineral Hill, NSW
Mineral Hill, NSW
Live
Live
100%
100%
EL
ML
100 UNITS
32.37 HA
ML5267
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML5278
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML332
Mineral Hill, NSW
Live
100%
ML
22.36 HA
ML333
Mineral Hill, NSW
Live
100%
ML
28.03 HA
ML334
Mineral Hill, NSW
Live
100%
ML
21.04 HA
ML335
Mineral Hill, NSW
Live
100%
ML
24.79 HA
ML336
Mineral Hill, NSW
Live
100%
ML
23.07 HA
ML337
Mineral Hill, NSW
Live
100%
ML
32.27 HA
ML338
Mineral Hill, NSW
Live
100%
ML
26.3 HA
ML339
Mineral Hill, NSW
Live
100%
ML
25.09 HA
ML340
Mineral Hill, NSW
Live
100%
ML
25.79 HA
ML1695
Mineral Hill, NSW
Live
100%
ML
8.779 HA
ML1712
Mineral Hill, NSW
Live
100%
ML
23.92 HA
ML1778
Mineral Hill, NSW
Live
100%
ML
29.05 HA
ML5499
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML5621
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML5632
Mineral Hill, NSW
Live
100%
ML
27.32 HA
ML6329
Mineral Hill, NSW
Live
100%
ML
8.094 HA
ML6365
Mineral Hill, NSW
Live
100%
ML
2.02 HA
www.kingstonresources.com.au
11
About Kingston Resources
Kingston Resources is currently producing gold from its Mineral Hill gold and copper mine in NSW and is developing the
3.8Moz Misima Gold Project in PNG. The Company’s objective is to establish itself as a mid-tier gold and base metals
company with multiple producing assets.
•
•
•
•
•
•
•
•
•
•
Mineral Hill Mine, NSW (100%)
Mine plan out to the end of 2027: Open pit and underground mining.
Significant upside: Current life of mine only utilises 22% of the current
8.9Mt of Mineral Resources.
Infrastructure excellence: Extensive existing infrastructure with all
permits and approvals in place.
Exploration potential: Exceptional upside within current Mining Leases
(ML) and Exploration Licenses (EL).
Current Focus: Maximising returns from Tailings Project gold production,
proactive exploration drilling, and underground re-entry.
Misima Gold Project, PNG (100%)
DFS Validation: potential for a robust, scalable, and low-cost open pit
operation.
Production Potential: Anticipated gold production of ~2.4Moz over a 20Year Mine Life (Avg. 128kozpa).
Strong Financial Viability: Pre-Tax Net Present Value (NPV) of A$956
Million (based on a US$1,800/oz Gold Price).
Gold Price Upside: Highly leveraged to the upside of the gold price,
amplifying potential returns.
Current Focus: Prioritising ESIA reports, strategic funding &
development strategies.
Mineral Hill is a gold and copper mine located in the Cobar Basin of NSW. In June 2023, the company updated its life of
mine plan, including both open pit and underground mining until 2027. The processing plant currently operates a CIL,
and work is underway to recommission the existing crushing, grinding and flotation circuits for copper, lead and zinc
concentrate production. In addition to current production, the company is focused on meeting near mine production
targets located on the existing MLs. The aim is to extend the mine’s life through organic growth and consider regional
deposits that could be processed at Mineral Hill’s processing plant.
Misima hosts a JORC Resource of 3.8Moz Au and an Ore Reserve of 1.73Moz. Placer Pacific operated Misima as a
profitable open pit mine between 1989 and 2001, producing over 3.7Moz before it was closed when the gold price was
below US$300/oz. The Misima Project also offers great potential for additional resource growth through exploration
success targeting extensions and additions to the current Resource base.
For further information regarding the Misima Mineral Resource and Ore Reserve estimate, see ASX announcements on
24 November 2020 and 15 September 2021 and 6 June 2022. Further information is included within the original
announcements.
The Mineral Hill Mineral Resource estimate outlined below was released in ASX announcements on 18 November 2021
(TSF), 15 March 2023 (Pearse South and Pearse North), 24 November 2022 (Southern Ore Zone), 21 March 2023 (Jack’s
Hut) and 13 September 2011(Parkers Hill by KBL). The Ore Reserve estimate outlined below was released in ASX
announcements on 18 November 2021 (TSF), 15 March 2023 (Pearse South and Pearse North). Further information is
included within the original announcements.
Kingston is not aware of any new information or data that materially affects the information included in this
announcement. All material assumptions and technical parameters underpinning the Mineral Resources and Ore
Reserve estimates continue to apply and have not materially changed.
www.kingstonresources.com.au
12
This release has been authorised by the Kingston Resources Limited Board. For all enquiries, please contact Managing Director,
Andrew Corbett, on +61 2 8021 7492.
Mineral Resources and Ore Reserves
Misima JORC 2012 Mineral Resource & Ore Reserve summary table
Resource Category
Cut-off (g/t Au)
Tonnes (Mt)
Gold Grade (g/t Au)
Silver Grade (g/t Ag)
Au (Moz)
Ag (Moz)
Indicated
0.3
97.7
0.79
4.3
2.5
13.4
Inferred
0.3
71.3
0.59
3.8
1.4
8.7
Total
0.3
169
0.71
4.1
3.8
22.1
Reserve
Cut-off (g/t Au)
Tonnes (Mt)
Gold Grade (g/t Au)
Silver Grade (g/t Ag)
Au (Moz)
Ag (Moz)
Probable
0.3
75.6
0.79
4.2
1.73
4.1
Mineral Hill JORC 2012 & JORC 2004 Mineral Resource & Ore Reserve summary table
Resource
Category
Measured
Tonnes
(kt)
228
Gold
Grade
(g/t)
2.11
Silver
Grade
(g/t)
11
Cu %
1.3%
Pb %
0.5%
Zn %
0.3%
Au (koz)
15
Ag (koz)
80
Cu (kt)
3
Pb (kt)
1.2
Zn (kt)
0.7
Indicated
5,582
1.06
28
1.2%
1.7%
1.1%
191
4,244
47
70
42
Inferred
3,091
1.17
23
0.7%
1.4%
1.2%
116
2,242
22
42
38
Total
8,901
1.13
26
1.0%
1.6%
1.1%
323
6,566
72
113
81
Reserve
Category
Proved
Tonnes
(kt)
-
Gold
Grade
(g/t)
0.00
Silver
Grade
(g/t)
0
Cu %
Pb %
Zn %
Au (koz)
-
Ag (koz)
0
Cu (kt)
Pb (kt)
Zn (kt)
Probable
1,431
1.55
57
71
470
Total
1,431
1.55
57
71
470
Competent Persons Statement and Disclaimer
The information in this report that relates to Exploration Results and Mineral Resources is based on information compiled by Mr. Stuart
Hayward BAppSc (Geology) MAIG, a Competent Person who is a member of the Australian Institute of Geoscientists. Mr. Hayward is an
employee of the Company. Mr. Hayward has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr. Hayward confirms that the information in the
market announcement provided is an accurate representation of the available data and studies for the material mining project and
consents to the inclusion in this report of the matters based upon the information in the form and context in which it appears.
The Competent Person signing off on the overall Misima Ore Reserves Estimate is Mr John Wyche BE (Min Hon), of Australian Mine
Design and Development Pty Ltd, who is a Fellow of the Australasian Institute of Mining and Metallurgy and who has sufficient relevant
experience in operations and consulting for open pit metalliferous mines. Mr Wyche consents to the inclusion in this report of the
information pertaining to the Misima Ore Reserve in the form and context in which it appears.
The Competent Person signing off on the overall Pearse Opencut Ore Reserves Estimate is Mr John Wyche BE (Min Hon), of Australian
Mine Design and Development Pty Ltd, who is a Fellow of the Australasian Institute of Mining and Metallurgy and who has sufficient
relevant experience in operations and consulting for open pit metalliferous mines. Mr Wyche consents to the inclusion in this report of
the information pertaining to the Pearse Opencut Ore Reserve in the form and context in which it appears.
www.kingstonresources.com.au
13