QUARTERLY REPORT
31 January 2024
ABOUT KINGSTON
RESOURCES
Kingston Resources is a gold
producer, focused on building
a mid-tier gold and base
metals company, with current
production from the Mineral
Hill gold and copper mine in
NSW, and advancing its
flagship development asset,
the 3.8Moz Misima Gold
Project in PNG.
QUARTERLY ACTIVITIES REPORT
For the period ending 31 December 2023
HIGHLIGHTS
Mineral Hill Gold & Copper Mine, NSW
•
Mineral Hill has produced $24m of operating cash flow from the date of
acquisition in January 2022 to December 2023 .
•
December Quarter production:
CAPITAL STRUCTURE
Shares on Issue: 497.9M
Market Cap: A$41M
Cash:(31 December 2023)
A$10.5m
•
DIRECTORS &
MANAGEMENT
Mick Wilkes
Non-Executive Chairman
Andrew Corbett
Managing Director & CEO
Stuart Rechner
Non-Executive Director
Tony Wehby
Non-Executive Director
Stuart Hayward
Chief Geologist
Geoff Merrell
GM, Mineral Hill
•
www.kingstonresources.com.au
ABN: 11 060 156 452
E:info@kingstonresources.co
m.au
A: 202/ 201 Miller Street,
North Sydney, NSW
2060
Share Register:
LinkedIn: Kingston Resources
Limited
Twitter: @KSNResources
o
Average gold price A$3,041/oz
o
AISC of A$2,302/oz
o
A$11.2m in sales and A$2.64m in operating cash flow.
o
Near mine discovery into a new lode underground, showing potential to
expand the life of mine.
o
Two drilling programs completed at the Southern Ore Zone (SOZ);.
o
High grade gold was intersected at the Eastern Ore Zone, with an
intersection of 3m @ 25.94g/t gold adjacent to existing underground
development.
o
An updated Mineral Resource and Ore Reserve estimate is planned for
SOZ in 2024.
Mine development:
o
Process plant refurbishment is progressing well, within budget and with
re-commissioning scheduled to occur by June 2024.
o
Access to the underground development has been fully re-established in
preparation for underground resource drilling with the decline pumped out,
ground support installed and primary ventilation operational.
o
Capital programs completed across the site are continuing to build
substantial value for the company.
Misima Gold Project, PNG
•
Kingston remains focused on bringing the project into production and
creating prosperity for all stakeholders.
•
Discussions are continuing with numerous interested parties in relation to
potential partnerships and development pathways.
Corporate
•
www.kingstonresources.com.au
Gold sold 3,627oz
Exploration:
CORPORATE DETAILS
ASX: KSN
o
Cash balance $10.5M as at 31 December 2023.
1
Kingston Managing Director, Andrew Corbett, said:
"I am pleased to provide you with a comprehensive update on our company's performance for the fourth quarter
of 2023. The past three months have continued to be a period of significant achievement for Kingston
Resources.
The Company has made significant progress during the quarter in our exploration and drilling activities at the
Mineral Hill Mine in New South Wales. We have achieved multiple milestones, including the discovery of
additional high-grade polymetallic lodes at the Southern Ore Zone (SOZ), intersection of zones of continuous
high grade gold at the Eastern Ore Zone (EOZ) and the advancement of our capital programs across the site.
It is an exciting time to be a gold producer in NSW. The market is experiencing renewed strength in the gold
price and the company is capitalising on spot gold prices for our gold and silver production. Junior mining
companies are facing numerous challenges in the current market, but having a producing asset within the
portfolio provides substantial stability and financial strength. Kingston’s sales of $11.2m over the quarter
demonstrates this strength clearly.
The exploration work has the potential to significantly expand our underground Mineral Resources and extend
the overall life of mine. We have focused our investment on re-establishing multiple cash producing orebodies
across the site which will build substantial value for the company.
With the successful milestones achieved and ongoing efforts, Kingston Resources is optimistic about the future
and the opportunities that lie ahead." - Managing Director, Kingston Resources
Figure 1: Board review on the progress of process plant refurbishment on July 23
www.kingstonresources.com.au
2
MINERAL HILL MINE
Exploration
During the quarter, Kingston made a material step forward in its exploration and drilling activities at the
Mineral Hill mine in New South Wales. The company achieved multiple milestones, including high-grade
polymetallic assays at the SOZ, near mine discoveries, and exploration drilling at SOZ and the Eastern Ore
Zone (EOZ). These developments have the potential to expand the underground Mineral Resources and
extend the company's life of mine inventory.
Southern Ore Zone
In October, Kingston conducted surface diamond
drilling at the SOZ, which resulted in wide, high-grade
portions indicating a strong potential for favorable
margins in underground production (See ASX
announcement on 11 October 2023).
Key highlights include 5m @ 5.37% CuEq and 5.5m
@ 3.83% CuEq. The mineralisation was observed
exactly where the existing Mineral Resource is
located, which has boosted the Company's
confidence in the geological model for this area.
In a subsequent drilling campaign, two new
mineralised structures were intersected to the east of
the SOZ Mineral Resource model (see ASX
announcement on 1 November 2023). Structure #1
Figure 2: Near mine discovery in KSNDDH017 (200mN crosssection, +-50m window).
was identified in historical drill holes and further
confirmed through the recent drilling (see Figure 2).
Additionally, a second high-grade polymetallic
mineralised structure was intersected, revealing the
discovery of a new zone of mineralisation (Structure
#2). Significant assays over this zone returned 12.5m
@ 3.41% CuEq.
Figure 3: SOZGT02 significant intersections (325mN cross-section,
+-12.5m window).
www.kingstonresources.com.au
A further six holes for 1,572.5m were drilled late in
the quarter and into January to test the upper extents.
The drilling aimed to increase the confidence Mineral
Resource Estimate, which is currently Inferred and
Indicated in these areas. Assay results are expected
to be returned in the March quarter. The Southern
Ore Zone currently has a Mineral Resource estimate
of 3.8Mt at 1.29g/t Au, 19.2g/t Ag, 0.9% Cu, 1.6% Pb,
and 1.4% Zn (refer to ASX announcement on 24
November 2022).
3
Table 1: Key highlights from hole KSNDDH017, Southern Ore Zone, Mineral Hill.
Hole ID
Interval
(m)
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
KSNDDH017
1.00
22.00
2.00
1.00
3.55
2.60
0.80
4.00
6.00
1.00
1.00
3.00
1.00
5.00
4.00
12.50
4.00
4.00
1.00
incl
incl
incl
incl
incl
incl
incl
From
(m
DH)
243
266
266
274
284
314
315
324
333
337
377
384
385
393
393
405
406.5
413.5
436
To
(m
DH)
244
288
268
275
287.55
316.6
315.8
328
339
338
378
387
387
398
397
417.5
410.5
417.5
437
Au
(g/t)
Ag
(g/t)
Cu
(%)
Pb
(%)
Zn
(%)
CuEqIS
(%)
CuEq
(%)
CuEqIS %
COG
0.02
0.53
1.29
2.66
0.44
0.13
0.25
0.07
0.11
0.01
0.1
0.46
0.61
0.59
0.72
0.11
0.12
0.06
0.03
81
20
30
24
37
33
32
10
13
2
5
18
24
7
8
17
28
22
10
0.02
0.47
0.40
0.26
1.24
0.19
0.37
0.14
0.04
0.00
0.03
0.25
0.36
0.26
0.28
2.10
4.40
1.85
0.35
0.03
2.22
3.12
1.14
6.12
2.02
2.92
1.90
1.15
0.17
0.38
0.47
0.62
1.14
1.31
3.67
4.26
6.77
2.70
0.10
1.20
4.27
0.62
1.93
2.83
3.44
2.18
3.84
0.60
0.94
1.00
0.69
1.21
1.22
4.50
4.88
8.30
0.21
0.71
1.87
3.60
2.60
3.84
1.95
2.60
1.44
1.77
0.27
0.54
1.12
1.30
1.36
1.51
4.66
7.32
6.41
1.12
0.46
1.38
2.52
1.95
2.89
1.32
1.80
0.98
1.13
0.17
0.36
0.80
0.95
0.98
1.10
3.41
5.51
4.54
0.87
0.5
1.0
2.5
2.5
2.5
0.5
1.0
1.0
0.5
1.0
0.5
0.5
1.0
0.5
1.0
0.5
1.0
2.5
1.0
* DD cut core samples (Half core HQ3, Quarter core PQ3). 0.3m min to 1m max sample intervals. FAS 50g + 4 Acid Digest-ICP. QAQC checked and verified
(Au + BM CRM, Pulp Blanks, Duplicates, Sample weights, DGPS Collar Locations, Single Shot Downhole surveys, Data verification).
**Drill hole intervals are reported as continuous zones at CuEqIS cut off grade of greater than 0.5%,1.0% and 2.5%, with 2 metres maximum internal waste
and minimum interval of 0.3mdh.
*** Mineralised intercepts for reporting are derived from In-Situ Copper Equivalent (CuEqIS) using the following formula. Proportions are based on KSN
forward looking USD$ commodity pricing and are not inclusive of metallurgical recovery.
CuEqIS%= (Au_ppm*0.63)+ (Ag_ppm*0.0078)+ (Cu%*1.0)+ (Pb%*0.224)+ (Zn%*0.342)
**** Assays and mineralised intercepts for KSNDDH017 are considered as final.
Eastern Ore Zone
Strong potential exists for Kingston to re-enter the existing underground development at the Eastern Ore
Zone, where high grade gold-copper was historically mined. Assay results from a two-hole drilling program
confirmed the presence of a continuous lode that extends along strike and down-plunge. Among the key
highlights was an interval of 3m @ 25.94g/t gold. This intersection is on the same structure as other insitu
high grade gold hits.
Kingston has commenced updating the Mineral Resource estimates for the near term production areas (open
pit and underground). The mineralisation at the EOZ is not included in the Company's current Mineral
Resources, but there is potential to include the area in updated estimates given access to the underground
development has been re-established.
With the positive results from the recent drilling activities, Kingston Resources is optimistic about the potential
to expand its Mineral Resources and extend the life of mine at Mineral Hill. The company will continue its
exploration efforts, conducting further drilling to assess the extensions and infill zones. Kingston Resources
remains committed to maximising the value of its mining operations and delivering long-term sustainable
growth.
www.kingstonresources.com.au
4
Figure 4: Long section view of Eastern Ore Zone (EOZ) showing extension potential.
Operations
Mineral Hill remains a foundational asset for Kingston as the company continues to produce ongoing cashflow
from the tailings retreatment project. Since acquiring the project in January 2022, Kingston has produced
$24m of operating cashflow from the site.
Key operational activities during the quarter included mining and processing from Tailings Storage Facility 1
(TSF1), building additional capacity in in TSF2 with a new wall lift and refurbishment of the processing plant.
Additionally, water was pumped out of the underground declines to gain access to the access drive at the
Southern Ore Zone. These capital programs are renewing the asset value across the site and setting the
company up for future operating cash flows.
Over the life of the project so far, the average feed grade has been higher than the original Ore Reserve
estimate. Mining and processing experienced a number of challenges during the quarter. Firstly, elevated
copper and lead gradesimpacted the gold feed grade, recoveries and the ability to maintain tonnage
throughput. Additionally, there were unplanned maintenance issues for the dozers, dragflow1 and the agitator
blades within the processing plant, which also affected throughput levels. Kingston has resolved these issues
by adding an additional dozer to maintain equipment availability, upgrading the hydraulic motors on the
dragflow and replacing the agitator blades. The company has also recruited a new manager for Assets and
Special Projects to focus on dragflow performance and mill supply.
Electrical storms caused significant disruption during the quarter, with rapid rain events and regional power
outages causing material downtime in the process plant. Additionally down time was caused by safety
standdowns related to lightning proximity.
1
Dragflow is a submersible pump which turns the tailings into a slurry so it can be piped to the processing plant.
www.kingstonresources.com.au
5
The rise in AISC from the previous quarter can mainly be attributed to the reduction in gold sold, but also due
to the additional sustaining capital costs in preparation for transitioning to open pit and underground mining.
The Company continues to realise the benefit of selling gold at spot prices, with the average realised gold
price increasing 3.7% to $3,041/oz.
Table 2: December 2023 quarter production summary.
September Quarter
December Quarter
Q on Q change
146,910
136,531
-7.1%
Average Feed Grade (g/t)
1.51
1.34
-11.0%
Processing Recovery (%)
59%
58%
-2.4%
Gold Production (oz)
4,229
3,409
-19.4%
Gold Sales (oz)
4,167
3,627
-13.0%
Silver Sales (oz)
5,154
5,685
10.3%
AISC (A$/oz)
$1,830
$2,302
25.8%
Realised Gold Price (A$/oz)
$2,933
$3,041
3.7%
Sales (A$m)
$12.37
$11.20
-9.5%
Operating Cashflow (A$m)
$4.56
$2.64
-42.0%
Tonnes Processed (t)
Gold Sold (oz)
AISC (A$/oz)
Realised Gold Price (A$/oz)
Gold Sales (oz) and AISC (A$/oz)
6,000
5,000
4,000
3,000
2,770
2,968
2,933
2,000
3,041
2,302
1,837
1,000
1,543
1,494
MarQ FY23
Jun Q FY23
Sep Q FY24
DecQ FY24
Figure 5: Quarterly gold sold, AISC and realised gold price.
Capital Programs
Re-entry works at the underground mining areas included pumping water down to the Southern Ore Zone
access drives, completing all necessary ground support and installing power and other services to the work
areas. The drives are now ready for underground resource drilling to commence over the next few months.
www.kingstonresources.com.au
6
Portal
Parkers
Hill
Red
Terror
Drill site 1
Southern Ore Zone
(SOZ)
Figure 6: Oblique long-section of the rehabilitated EOZ Decline and SOZ Access drives.
The refurbishment of the processing plant at
Mineral Hill is progressing well and within
budget. Major work during the quarter
included numerous steel replacements
across the fine ore bins and some structural
pillars. Clean-outs of the conveyors and
flotation circuits was also completed.
Kingston has maintained an “act like an
owner” mentality in optimising these projects
in terms of cost reduction and adherence to
schedules.
Safety,
Environment
Sustainability
and
There were no reportable environmental or
safety incidents during the quarter.
MISIMA GOLD PROJECT
Kingston remains committed to realising the
best value from the Misima Gold Project,
which centres around bringing the project
into production and creating prosperity for all
stakeholders. The company has been in
discussions with numerous interested
parties in relation to potential partnerships
and development arrangements.
Figure 7: Refurbished conveyor tunnel from the fine ore bins up to the ball mills.
www.kingstonresources.com.au
7
CORPORATE
The Company’s closing cash balance at 31 December 2023 was $10.5 million in unrestricted cash and a
further $7.2 million in restricted cash (environmental bonds). The consolidated group cash flow for the quarter
is summarised below:
Net cash from/(used in)
Gross revenue ($m)
11.260
Production cost ($m)
(5.060)
Staff cost ($m)
(1.780)
Administration and corporate cost ($m)
(0.081)
Net interest payment ($m)
(0.388)
Net cash flow from operating activities($m)
3.940
Exploration and development expenditure ($m)
(0.975)
Net cash flow from investing activities ($m)
(7.23)
Net cash flow from financing activity ($m)
(0.090)
During the quarter, the Company made payments totaling $172,000 to associates or related parties reflecting
fees, wages, and superannuation paid to Directors.
www.kingstonresources.com.au
8
Table 3: Tenement Schedule (ASX LR 5.3.3) as at end of quarter
Tenement
Status
Ownership
Type
Title Area
EL1747
Misima, PNG
Live
100%
EL
180 km2
EL1999
Mineral Hill, NSW
Live
100%
EL
17 UNITS
EL8334
ML5240
Mineral Hill, NSW
Mineral Hill, NSW
Live
Live
100%
100%
EL
ML
100 UNITS
32.37 HA
ML5267
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML5278
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML332
Mineral Hill, NSW
Live
100%
ML
22.36 HA
ML333
Mineral Hill, NSW
Live
100%
ML
28.03 HA
ML334
Mineral Hill, NSW
Live
100%
ML
21.04 HA
ML335
Mineral Hill, NSW
Live
100%
ML
24.79 HA
ML336
Mineral Hill, NSW
Live
100%
ML
23.07 HA
ML337
Mineral Hill, NSW
Live
100%
ML
32.27 HA
ML338
Mineral Hill, NSW
Live
100%
ML
26.3 HA
ML339
Mineral Hill, NSW
Live
100%
ML
25.09 HA
ML340
Mineral Hill, NSW
Live
100%
ML
25.79 HA
ML1695
Mineral Hill, NSW
Live
100%
ML
8.779 HA
ML1712
Mineral Hill, NSW
Live
100%
ML
23.92 HA
ML1778
Mineral Hill, NSW
Live
100%
ML
29.05 HA
ML5499
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML5621
Mineral Hill, NSW
Live
100%
ML
32.37 HA
ML5632
Mineral Hill, NSW
Live
100%
ML
27.32 HA
ML6329
Mineral Hill, NSW
Live
100%
ML
8.094 HA
ML6365
Mineral Hill, NSW
Live
100%
ML
2.02 HA
www.kingstonresources.com.au
Project Name & Location
9
About Kingston Resources
Kingston Resources is currently producing gold from its Mineral Hill gold and copper mine in NSW and is developing the
3.8Moz Misima Gold Project in PNG. The Company’s objective is to establish itself as a mid-tier gold and base metals
company with multiple producing assets.
•
•
•
•
•
•
•
•
•
•
Mineral Hill Mine, NSW (100%)
Mine plan out to the end of 2027: Open pit and underground mining.
Significant upside: Current life of mine only utilises 22% of the current
8.9Mt of Mineral Resources.
Infrastructure excellence: Extensive existing infrastructure with all
permits and approvals in place.
Exploration potential: Exceptional upside within current Mining Leases
(ML) and Exploration Licenses (EL).
Current Focus: Maximising returns from Tailings Project gold production,
proactive exploration drilling, and underground re-entry.
Misima Gold Project, PNG (100%)
DFS Validation: potential for a robust, scalable, and low-cost open pit
operation.
Production Potential: Anticipated gold production of ~2.4Moz over a 20Year Mine Life (Avg. 128kozpa).
Strong Financial Viability: Pre-Tax Net Present Value (NPV) of A$956
Million (based on a US$1,800/oz Gold Price).
Gold Price Upside: Highly leveraged to the upside of the gold price,
amplifying potential returns.
Current Focus: Prioritising ESIA reports, strategic funding &
development strategies.
Mineral Hill is a gold and copper mine located in the Cobar Basin of NSW. In June 2023, the company updated its life of
mine plan, including both open pit and underground mining until 2027. The processing plant currently operates a CIL,
and work is underway to recommission the existing crushing, grinding and flotation circuits for copper, lead and zinc
concentrate production. In addition to current production, the company is focused on meeting near mine production
targets located on the existing MLs. The aim is to extend the mine’s life through organic growth and consider regional
deposits that could be processed at Mineral Hill’s processing plant.
Misima hosts a JORC Resource of 3.8Moz Au and an Ore Reserve of 1.73Moz. Placer Pacific operated Misima as a
profitable open pit mine between 1989 and 2001, producing over 3.7Moz before it was closed when the gold price was
below US$300/oz. The Misima Project also offers great potential for additional resource growth through exploration
success targeting extensions and additions to the current Resource base.
For further information regarding the Misima Mineral Resource and Ore Reserve estimate, see ASX announcements on
24 November 2020 and 15 September 2021 and 6 June 2022. Further information is included within the original
announcements.
The Mineral Hill Mineral Resource estimate outlined below was released in ASX announcements on 18 November 2021
(TSF), 15 March 2023 (Pearse South and Pearse North), 24 November 2022 (Southern Ore Zone), 21 March 2023 (Jack’s
Hut) and 13 September 2011(Parkers Hill by KBL). The Ore Reserve estimate outlined below was released in ASX
announcements on 18 November 2021 (TSF), 15 March 2023 (Pearse South and Pearse North). Further information is
included within the original announcements.
Kingston is not aware of any new information or data that materially affects the information included in this
announcement. All material assumptions and technical parameters underpinning the Mineral Resources and Ore
Reserve estimates continue to apply and have not materially changed.
www.kingstonresources.com.au
10
This release has been authorised by the Kingston Resources Limited Board. For all enquiries, please contact Managing Director,
Andrew Corbett, on +61 2 8021 7492.
Mineral Resources and Ore Reserves
Misima JORC 2012 Mineral Resource & Ore Reserve summary table
Resource Category
Cut-off (g/t Au)
Tonnes (Mt)
Gold Grade (g/t Au)
Silver Grade (g/t Ag)
Au (Moz)
Ag (Moz)
Indicated
0.3
97.7
0.79
4.3
2.5
13.4
Inferred
0.3
71.3
0.59
3.8
1.4
8.7
Total
0.3
169
0.71
4.1
3.8
22.1
Reserve
Cut-off (g/t Au)
Tonnes (Mt)
Gold Grade (g/t Au)
Silver Grade (g/t Ag)
Au (Moz)
Ag (Moz)
Probable
0.3
75.6
0.79
4.2
1.73
4.1
Mineral Hill JORC 2012 & JORC 2004 Mineral Resource & Ore Reserve summary table
Resource
Category
Measured
Tonnes
(kt)
228
Gold
Grade
(g/t)
2.11
Silver
Grade
(g/t)
11
Cu %
1.3%
Pb %
0.5%
Zn %
0.3%
Au (koz)
15
Ag (koz)
80
Cu (kt)
3
Pb (kt)
1.2
Zn (kt)
0.7
Indicated
5,582
1.06
28
1.2%
1.7%
1.1%
191
4,244
47
70
42
Inferred
3,091
1.17
23
0.7%
1.4%
1.2%
116
2,242
22
42
38
Total
8,901
1.13
26
1.0%
1.6%
1.1%
323
6,566
72
113
81
Reserve
Category
Proved
Tonnes
(kt)
-
Gold
Grade
(g/t)
0.00
Silver
Grade
(g/t)
0
Cu %
Pb %
Zn %
Au (koz)
-
Ag (koz)
0
Cu (kt)
Pb (kt)
Zn (kt)
Probable
1,431
1.55
57
71
470
Total
1,431
1.55
57
71
470
Competent Persons Statement and Disclaimer
The information in this report that relates to Exploration Results and Mineral Resources is based on information compiled by Mr. Stuart
Hayward BAppSc (Geology) MAIG, a Competent Person who is a member of the Australian Institute of Geoscientists. Mr. Hayward is an
employee of the Company. Mr. Hayward has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr. Hayward confirms that the information in the
market announcement provided is an accurate representation of the available data and studies for the material mining project and
consents to the inclusion in this report of the matters based upon the information in the form and context in which it appears.
The Competent Person signing off on the overall Misima Ore Reserves Estimate is Mr John Wyche BE (Min Hon), of Australian Mine
Design and Development Pty Ltd, who is a Fellow of the Australasian Institute of Mining and Metallurgy and who has sufficient relevant
experience in operations and consulting for open pit metalliferous mines. Mr Wyche consents to the inclusion in this report of the
information pertaining to the Misima Ore Reserve in the form and context in which it appears.
The Competent Person signing off on the overall Pearse Opencut Ore Reserves Estimate is Mr John Wyche BE (Min Hon), of Australian
Mine Design and Development Pty Ltd, who is a Fellow of the Australasian Institute of Mining and Metallurgy and who has sufficient
relevant experience in operations and consulting for open pit metalliferous mines. Mr Wyche consents to the inclusion in this report of
the information pertaining to the Pearse Opencut Ore Reserve in the form and context in which it appears.
www.kingstonresources.com.au
11