Investor Presentation-Misima Divestment & Corporate Outlook
Released
Released
Announcement PDF
Kingston Resources Limited
Misima Divestment and Corporate
Outlook
ACCELERATING MINERAL HILL GOLD-COPPER
GROWTH AND DEVELOPMENT
20 MAY 2025
www.kingstonresources.com.au I ASX: KSN
1
Important Notices
and Disclaimer
Corporate Presentation | May 2025
2
Important notices and disclaimer
Forward Looking Statements
Mineral Hill Gold Bar
Certain statements contained in this presentation, including information as to the future financial or operating performance of KSN and its projects, are
forward looking statements. Such forward looking statements: include, among other things, statements regarding incomplete and uncertain proposals or
targets, production and prices, operating costs and results, capital expenditures, and are or may be based on assumptions and estimates related to future
technical, economic, market, political, social and other conditions; are necessarily based upon a number of estimates and assumptions that, while considered
reasonable by KSN, are inherently subject to significant technical, business, economic, competitive, political and social uncertainties and contingencies; and
involve known and unknown risks and uncertainties that could cause actual events or results to differ materially from estimated or anticipated events or
results reflected in such forward looking statements.
KSN disclaims any intent or obligation to update publicly any forward-looking statements, whether as a result of new information, future events or results or
otherwise. The words “believe”, “expect”, “anticipate”, “indicate”, “contemplate”, “target”, “scope”, “plan”, “intends”, “continue”, “budget”, “estimate”,
“may”, “will”, “schedule” and similar expressions identify forward looking statements. All forward looking statements made in this presentation are qualified
by the foregoing cautionary statements. Recipients are cautioned that forward looking statements are not guarantees of future performance and accordingly
investors are cautioned not to put undue reliance on forward looking statements due to the inherent uncertainty therein.
Disclaimer
No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions and
conclusions contained in this presentation. To the maximum extent permitted by law, none of KSN, its directors, employees or agents, nor any other person
accepts any liability, including, without limitation, any liability arising out of fault of negligence, for any loss arising from the use of the information contained
in this presentation. In particular, no representation or warranty, express or implied is given as to the accuracy, completeness or correctness, likelihood of
achievement or reasonableness or any forecasts, prospects or returns contained in this presentation nor is any obligation assumed to update such
information. Such forecasts, prospects or returns are by their nature subject to significant uncertainties and contingencies.
The information contained in this presentation is for informational purposes only and does not constitute an offer to issue, or arrange to issue, securities or
other financial products. The information contained in this presentation is not investment or financial product advice and is not intended to be used as the
basis for making an investment decision. The presentation has been prepared without taking into account the investment objectives, financial situation or
particular needs of any particular person. Before making an investment decision, you should consider, with or without the assistance of a financial adviser,
whether an investment is appropriate in light of your particular investment needs, objectives and financial circumstances. Past performance is no guarantee
of future performance.
For further information on the Life of Mine at Mineral Hill referred to in this Presentation, refer to the Company’s ASX Announcement dated 27 June 2023 and
30 September 2024
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
3
Important notices and disclaimer
Exploration by Other Explorers
This presentation contains information sourced from the reports of other Explorers. References to the original reports are provided as footnotes where the information is cited in this
presentation. KSN does not vouch for the accuracy of these reports. KSN has taken the decision to include this information as it is in the public domain and as we assess it to be of relevance to
shareholders and investors.
Production Target
The LOM plan includes Mineral Resource Estimates for Pearse pits, the Southern Ore
Zone (SOZ) and Jack’s Hut to estimate the Production Target1. All Ore Reserves and
Mineral Resources underpinning this LOM plan have been prepared by Competent
Persons in accordance with the 2012 JORC reporting guidelines. The Production
Target comprises 51% Ore Reserves, 11% Measured & Indicated Resources and 38%
Inferred Resources. The first 12 and 36 months of the Production Target are
underpinned by 89% and 80% of Measured and Indicated Resources respectively
There is a low level of confidence associated with Inferred Mineral Resources and
there is no certainty that further exploration work will result in the determination of
Indicated Mineral Resources or that the production target itself will be realised.
The stated production target is based on the Company’s current expectations of
future results or events and should not be solely relied upon by investors when
making investment decisions. Further evaluation work and appropriate studies are
required to establish sufficient confidence that this target will be met. The Company
notes that the Project forecasts a positive financial performance and is therefore
satisfied that the use of Inferred resources in production target reporting and forecast
financial information is not the determining factor in overall Project viability and that
it is reasonable to report the LOM plan with Inferred Resources.
The Company has concluded that it is has a reasonable basis for providing the
forward-looking statements included in this announcement. The detailed reasons for
that conclusion are outline throughout this presentation.
1. See ASX Announcement dated 27 June 2023, 2 April 2024 and 30 Sept 2024, for further detail and key assumptions
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
4
Mineral Hill – Processing Facility
2
Kingston Investment
Highlights
Corporate Presentation | May 2025
5
Kingston Resources: Investment highlights
Existing gold and silver producer: Mineral Hill copper
production commencing FY26, Resource of 760koz AuEq1,
open pit and underground Ore Reserves
Strong balance sheet: Transaction to divest Misima agreed
for total consideration of $95 million
Significant expansion potential: Infill, extensional and
near mine exploration drilling underway
Strategic infrastructure: Opportunity to unlock regional
deposits − the only processing solution in southern Cobar
1. See slide on metal equivalents for AuEq and CuEq calculations.
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
6
The Mineral Hill story so far
Transformative return on investment and growth
Fully approved with a six-year mine
life and multiple targets to extend
Dec-27
Jun-27
Dec-26
Jun-26
Dec-25
Jun-25
Life of mine out to 2031 – 6 years
Dec-24
Mineral Hill has delivered 42koz of
gold sales and $38m in operating
cash to date1
Open Pit Mining
Open Pit Processing
$14m plant refurbishment complete
and government approvals in place
to expand processing to 700ktpa
Investing in local businesses and the
community with $31m of
Condobolin region expenditure1
UG Mining
UG Processing
1. Reporting period from Jan 2022 to Mar 2025
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
7
Misima Gold Mine – circa 1995
3
Transaction Overview
Corporate Presentation | May 2025
8
Misima transaction overview
Successful strategic process delivers significant value for shareholders
Transaction
Overview
• Kingston Resources Limited has entered into a binding definitive agreement to divest the Misima Gold-Silver Project (Misima or the Project) to 100% PNG
owned Ok Tedi Mining Limited (Ok Tedi) (the Transaction).
• The Transaction will be effected via the sale of Kingston’s wholly owned subsidiary Gallipoli Exploration (PNG) Limited (Gallipoli), which holds a 100%
interest in the Project.
Transaction
Consideration
• Under the Transaction, Kingston will receive total consideration of $95 million comprising:
• $50 million in upfront cash, payable on completion of the Transaction;
• $10 million in deferred cash, payable 12 months post completion of the Transaction;
• $10 million in deferred cash, payable on a positive final investment decision (FID) to proceed with the commercial scale development of Misima;
and a
• 0.5% gross revenue royalty, payable on future gold and copper production from Misima (Royalty), indicatively valued at $25 million.
• The Royalty will be uncapped and commence after 500koz of gold or gold equivalent has been produced from the Project. The Royalty will be subject to a
buy-back right to Ok Tedi for a value of $25 million.
Approvals /
Conditions
• No shareholder approvals (Kingston or Ok Tedi) are required for completion of the Transaction.
• The Transaction is not subject to any financing conditions with consideration to be sourced from existing cash and future cash flows from the Ok Tedi Mine.
• Completion of the Transaction remains subject to the following conditions precedent being satisfied or waived by Ok Tedi:
• Receipt of approval from the Independent Consumer & Competition Commission (ICCC);
• No material adverse change including renewal of exploration licence EL 1747 not being rejected by the Mineral Resources Authority or otherwise
forfeited, cancelled or materially varied; and
• Other terms and conditions customary for an agreement of this nature, including standard representations and warranties.
Completion
• Kingston anticipates the Transaction completing during Q1, FY26 following receipt of ICCC approval.
Advisors
• Argonaut PCF acted as financial advisor and Ashurst as legal advisor to Kingston in relation the Transaction.
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
9
Ok Tedi company overview
Ok Tedi Mining Limited operates the Ok Tedi Mine which is the longest running open-pit copper, gold and silver
mine in Papua New Guinea
• Ok Tedi is 67% owned by the Independent State of
PNG and 33% owned by the people of the Western
Province
OK TEDI
• The Ok Tedi Mine is a large-scale open pit coppergold asset producing a copper, gold, silver
concentrate
• Ok Tedi generated US$1.5b in revenue in 2024.
• The Ok Tedi Mine produces approximately 100ktpa
copper, 260kozpa gold and 1Mozpa silver and is
capable of processing up to 24Mtpa of ore, with Ok
Tedi currently expanding the mine life out to 2050.
• Ok Tedi was established in 1981 to mine the Mt.
Fubilan copper-gold ore body
• Since beginning operations, Ok Tedi has contributed
on average 6.2% of PNG’s GDP
www.kingstonresources.com.au I ASX: KSN
Misima
Mt. Fubilan – Mineral Resources
Cu (%)
Au (g/t)
Contained
Cu (kt)
Contained
Au (Moz)
Category
Tonnage (Mt)
Measured
105
0.70%
0.82
735
2.8
Indicated
301
0.54%
0.66
1625.4
6.4
Inferred
13
0.53%
0.68
68.9
0.3
Total
419
0.58%
0.7
2430.2
9.4
Corporate Presentation | May 2025
10
Transaction rationale
Kingston now positioned strongly for growth at Mineral Hill
Materially strengthened balance sheet with $50 million upfront transaction consideration resulting in a net cash position and
repayment of $15 million debt facility in full1
Total consideration is greater than Kingston’s market capitalisation whilst retaining 100% of Mineral Hill
Eliminates ongoing cash outflows of up to $4.0 million per year through removal of Misima and debt servicing costs
Balance sheet flexibility to accelerate infill and extensional drilling at Mineral Hill as well as regional exploration
Provides a strong platform to consider regional growth opportunities complimentary to Mineral Hill and beyond
Ongoing upside exposure to Misima with $10 million payable 12 months post completion; $10 million payable on FID2 to
develop Misima and a 0.5% uncapped gross revenue royalty3
1. Kingston intends to use its strong financial position to fully repay its existing $15 million secured debt facility with Pure Asset Management.
2. Final Investment Decision
3. Uncapped gross revenue royalty to commence after first 500koz of gold or gold equivalent product has been produced. Royalty is subject to a buy-back right to Ok Tedi
for a value of $25m cash.
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
11
Corporate snapshot
1-Year Share Price Performance
Market Volume('000) RHS
Shares on issue
822m
Close Price (A$) (LHS)
0.12
Warrants & options2,3
168.4m
Share price (16/5/2025)
$0.09
0.08
Market cap
35,000
30,000
25,000
20,000
15,000
10,000
5,000
0
0.1
$76m
0.06
Cash @ 31 March 20251
$12.5m
0.04
Restricted cash for environmental bond
$7.4m
Debt4
$15m
0.02
0
Shareholder Structure
Delphi 14.5%
Quintana 8.1%
Winchester 7.9%
Farjoy 7.4%
1. Estimated Cash balance, as at 31 Mar 2025, excludes $7.4m cash backed environmental bond.
2. 38m unlisted options @ $0.14, exp 31 July 25.
3. 25m unlisted warrants @ $0.0816, exp 07 July 2027, 35.7m unlisted warrants @ $0.0816 exp 29 June 2028, 69.7m warrants @
$0.0879, exp 23 Feb 2028.
4. Debt payback - $5m matures 7 July 2026, $5m matures 23 February 2027,$5m matures 29 June 2027,
www.kingstonresources.com.au I ASX: KSN
Other 62%
Corporate Presentation | May 2025
12
Mineral Hill – Pearse North Open Pit
4
Mineral Hill
Expansion Plan
Corporate Presentation | May 2025
13
Mineral Hill expansion plan
De-risking and expanding the Mineral Hill operations through drilling
Target additional underground ore sources by leveraging the two existing underground mines and
immediately expand the current underground drilling program to extend the current six-year mine life
Undertake near mine surface exploration to target additional open pit and underground discoveries within
the current Mining Licence (ML) and EL 1999 with the aim of providing a medium-term ore source
Commence greenfields exploration on EL 8334 targeting a significant discovery
Strategically located in the southern Cobar Basin to provide a processing solution for third party ore and
pursue other accretive growth opportunities
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
14
Leveraging existing underground mines
Two existing underground mines with
declines and ventilation systems in place
Setting up the long-term future of Mineral Hill
• Underground mine life of +5 years
• Underground development set to commence early 2026
• Underground drilling program to be immediately expanded
to target an additional production source and extend mine
life
• Existing infrastructure and approvals in place to support
extension
Southern Ore Zone Underground Mineral Resources1
Class
Tonnes
kt
Cu
%
Pb
%
Zn
%
Au
g/t
Ag
g/t
Cu
kt
Pb
kt
Zn
kt
Au
koz
Ag
koz
Total
3,776 1.0
1.3
1.1
1.83
17 37
51
40
222 2,038
Southern Ore Zone Underground Ore Reserve2
Class
Tonnes
kt
Cu
%
Pb
%
Zn
%
Au
g/t
Ag
g/t
Cu
kt
Pb
kt
Zn
kt
Au
koz
Ag
koz
Probable
700 0.8
1.9
1.6
1.4
20 5.5
13
11
30
450
Long-hole open stopes
Oblique view of the Southern Ore Zone planned stopes
1. Due to rounding to appropriate significant figures, minor discrepancies may occur, tonnages are dry metric tonnes.
2. See ASX Announcement dated 30 September 2024,
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
15
Expanding underground drilling programs
Targeting resource extensions to increase mine life
• Underground diamond drilling at SOZ: commenced in Feb
2025 and to be immediately expanded post transaction
SOZ Underground diamond drilling
• Focus: infill and extension of existing resources, targeting both
stope shapes and high-grade lodes
• Resource potential: Targeting depths from 450m down to
1.8km, aligning with typical Cobar-style deposits
Mineral Hill
www.kingstonresources.com.au I ASX: KSN
Peak
Corporate Presentation | May 2025
16
To increase scale at Mineral Hill
Strategy on expanding Mineral Resources and making new discoveries
Brownfields expansion targets
Currently 7.2Mt of
underground resources
High grade gold
Plan:
GD140
Parkers Hill
EOZ
• Expand underground drilling
• Update Resource estimates
• Add other brownfields
deposits to the mine plan
(currently SOZ and Jack’s
Hut only)
Existing Production Target1
at SOZ
Jacks Hut
Copper - Gold
Key resource expansion projects:
• SOZ infill & extension drilling
• Parkers Hill resource update
• Jacks Hut and EOZ extensions
Recent discovery
12.5m @
3.41% CuEq
Copper-Gold
Infill
1. See ASX Announcement dated 21 March 2023 and 30 September 2024 for MRE announcements
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
17
Targeting additional discoveries
Near mine open pit and underground targets identified
on EL8334
4
5
EL1999
Surface drilling planned to target open pit and underground
prospects within the current ML and EL 1999
• Potential to extend mine life and provide a medium-term
ore source
• Increasing high margin feed stock adjacent to the plant
2.5km
Key target areas:
3
1 SOZ infill & extension drilling
2
2 Parkers Hill – GD140 resource updates
3
Jacks Hut and EOZ extension
4
Bogong target – drilling
5
Regional exploration on EL 8334 – Webers Gossan
Long Panel and China Workings
www.kingstonresources.com.au I ASX: KSN
EL1999
1
EL1999
Corporate Presentation | May 2025
18
Further potential at depth and regionally to be tested
Mineral Hill remains open at depth and along the regional trends
• Depth of drilling
<500m depth
• Major mineral
deposits in Cobar
extend to ~1.8km
• Numerous
regional
exploration
targets that will be
considered in
future drilling
(long section looking SW)
13km
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
19
Further resource growth opportunities regionally
Highly prospective greenfields drill targets and geochemical signatures provide significant upside
Focus on value-driven exploration:
• EL 8334: High-potential targets
• Strong soil & geophysical results
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
20
Strongly positioned to consider complementary opportunities
Mineral Hill is the only operating processing facility in the southern Cobar Basin
Grow resources and expand daily throughput
Today
1,000 tpd
360,000 tpa
Target
2,000 tpd
Target a
doubling of
production
700,000 tpa
c.70kozpa AuEq
Resource growth strategy
Mineral Hill
Extensions
Regional
Acquisition
Increase
grinding &
flotation
capacity
Regional Exploration
EL8334
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
21
Summary: Focus on ramping up Mineral Hill
Leveraging the existing gold-copper asset base while advancing future growth opportunities
Experienced Management Team: Focused on maximising
returns from Mineral Hill with strong balance sheet flexibility
Strategically Located: Mineral Hill positioned central to
copper & gold assets with no immediate processing solution
Increase Production Rate: Unlock additional cashflow and
production from open pit and underground mining
Strategic Advantage: Fully approved and operating
processing plant with multiple drill targets and growth
options
Accretive Growth: Ideally positioned to consider Australian
based copper and/or gold growth initiatives that complement
Mineral Hill operations
SOZ Underground Mine
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
22
Appendix
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
23
Highly experienced and well-regarded Executive Team
Significant experience across the development life cycle through to production
Mick Wilkes
Andrew Corbett
Tony Wehby
Stuart Rechner
Non-Executive Chairman
Managing Director
Non-Executive Director
Non-Executive Director
Mick is a seasoned mining
professional with 35 years’
experience in the industry,
primarily in gold and base
metals. He has specialised in
sustainable project
development, construction, and
operations throughout his
career.
Andrew is a highly experienced
mining engineer with over 25
years in mine management and
financial markets. He has an indepth understanding of mining,
equity markets, business
development and corporate
strategy.
Tony is a highly experienced
board member and chairman,
previously Non-Executive
Chairman of Tellus Resources
Limited and Aurelia Metals
Limited, and a Director of
Ensurance Ltd.
Stuart is an experienced
company director and geologist
with a background in project
generation and acquisition in
Australia and overseas. Mr
Rechner holds degrees in both
geology and law.
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
24
Building a safe and
sustainable culture
Investing in our people and
our community
A large employer in
Condobolin
ESG framework: safe,
responsible and sustainable
Investing in our local and
residential workforce
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
25
Mineral Hill – Social Licence
Environmental and Social Licence to operate
Permits in place for mining and processing
Cash backed environmental bonds
Tailings capacity in place and expansion plans scheduled
Biodiversity offset established
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
26
Competent Person Statement
Competent Person’s Statement - Mineral Resource Reported in Accordance with 2012 JORC Code – Mineral Hill
The information in this report that relates to the reporting of the Mineral Hill Mine Mineral Resource Estimate is based on and fairly represents, information and supporting documentation compiled by Mr. Stuart Hayward (BAppSc (Geology))
MAIG ,who is a Member of the Australian Institute of Geoscientists. Mr. Stuart Hayward is a full-time employee of Kingston Resources Limited. Mr. Hayward has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr. Hayward confirms
that the information in the market announcement provided is an accurate representation of the available data and studies for the material mining project and consents to the inclusion in this report of the matters based upon the information in the
form and context in which it appears. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original report.
Competent Person’s Statement - Mineral Resource Reported in Accordance with 2004 JORC Code – Mineral Hill
The information in this release that relates to Mineral Resources is based on information reviewed by Mr. Stuart Hayward (BAppSc (Geology)) MAIG, who is a Member of The Australian Institute of Geoscientists and a full-time employee of
Kingston Resources Limited. Mr Hayward has sufficient experience in the style of mineralisation and types of deposit under consideration and to the activity he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the
‘Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr. Hayward confirms that the information in the market announcement provided is an accurate representation of the available data and studies for the
material mining project and consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. All Mineral Resource estimates were prepared and first disclosed under the JORC Code 2004
and are an accurate representation of the available data and studies for the Mineral Hill Mine. This information has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it
was last reported. Work will commence on close of acquisition by the Company to bring each of the Mineral Resources into line with the JORC Code 2012.
Competent Person’s Statement – Ore Reserve Reported in Accordance with JORC Code – Mineral Hill
The Ore Reserve and Mineral Resources estimates were prepared by a Competent person in accordance with the JORC Code 2012 with exception of the Parkers Hill Mineral Resource Estimates that have been prepared by a Competent Person in
accordance with the JORC Code 2004 and have not been updated to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. Pearse, Parkers Hill, Jacks Hut and the Southern Ore
Zone Mineral Resource estimates and Ore Reserves have been adjusted by mining depletion using the production wireframes created by the site survey department at the time of mining. These wireframes represent the mining activities at these
deposits to the best of Kingston’s knowledge although they are not to be viewed as complete or accurate in their entirety and therefore mining depletion may be revised when Kingston is able to produce revised determinations on more complete
data and verification thereof. Information pertaining to Mineral Resource Estimates (MRE) and Ore Reserves (OR) in this presentation has been previously released to the public. The tables on this page indicate the authors of the historical
Resources/Reserves and the dates they were initially published. Kingston is not reporting these estimates as its own with exception of the MRE and OR for the TSF which has not been reported previously by any other company. The other original
reports are available through the ASX website.
The Competent Person signing off on the the overall Pearse Opencut Ore Reserves Estimate is Mr John Wyche BE (Min Hon) BComm CP, of Australian Mine Design and Development Pty Ltd, who is a Fellow of the AusIMM and who has sufficient
relevant experience in operations and consulting for open pit metalliferous mines. Mr Wyche consents to the inclusion in this report of the information pertaining Mineral Hill Pearse open pit Ore Reserves in the form and context in which it appears.
The Competent Person signing off on the overall underground SOZ Ore Reserves Estimate is Mr Steven Weckert BE ME (Min) CP, of Australian Mine Design and Development Pty Ltd, who is a Member of the AusIMM and who has sufficient
relevant experience in operations and consulting for underground metalliferous mines. Mr Weckert consents to the inclusion in this report of the information pertaining to the Mineral Hill SOZ Ore Reserve in the form and context in which it
appears.
Mineral Resource
Ore Reserve
Deposit
JORC
ASX Announcement
Competent Person
Company
Deposit
JORC
ASX Announcement
Competent Person
Company
Pearse North
2012
KSN 30/9/2024
John Wyche
AMDAD
Pearse South
2012
KSN 15/03/2023
Stuart Hayward
KSN
Pearse South
2012
KSN 30/9/2024
John Wyche
AMDAD
Pearse North
2012
KSN 7/05/2024
Stuart Hayward
KSN
SOZ
2012
KSN 30/9/2024
John Wyche
AMDAD
Southern Ore Zone
2012
KSN 30/09/2024
Stuart Hayward
KSN
Jack’s Hut
2012
KSN 21/03/2023
Stuart Hayward
KSN
Parkers Hill
2004
KBL 13/09/2011
Anthony Johnston
KBL
www.kingstonresources.com.au I ASX: KSN
Corporate Presentation | May 2025
27
Mineral Hill – Resources & Reserves
Attractive commodity base with significant growth potential
Total Probable Ore Reserves
Measured Resource Inventory
Kt
Au
(g/t)
Ag
(g/t)
Pearse South
140
4.30
85
19
383
Southern Ore Zone
233
2.01
11
1.2%
Pearse North
240
3.20
33
25
255
TOTAL
233
2.01
11
1.2%
700
1.40
20
0.8%
1.9%
1.6%
30
450
5.5
13
11
1,080
2.2
31
0.8%
1.9%
1.6%
74
1087
5.5
13
11
Deposit
Southern Ore Zone
TOTAL
Cu
%
Pb
%
Zn
%
Au
(Koz)
Ag
(Koz)
Cu
(Kt)
Pb
(Kt)
Zn
(Kt)
Total Mineral Resources
Deposit
Pearse South
•
•
•
•
•
Kt
204
Au
(g/t)
3.77
Ag
(g/t)
Cu
%
Pb
%
Zn
%
70
Au
(Koz)
25
Ag
(Koz)
Cu
(Kt)
Pb
(Kt)
Zn
(Kt)
456
Deposit
Kt
Au
(g/t)
Ag
(g/t)
Cu
%
Pb
%
Zn
%
Au
(Koz)
Ag
(Koz)
Cu
(Kt)
Pb
(Kt)
Zn
(Kt)
0.2%
0.4%
15
80.9
3
1
1
0.5%
0.4%
15
81
3
1
1
450
28
Indicated Resource Inventory
Pearse South
164
4.10
85
22
Pearse North
270
3.20
34
28
297
Southern Ore Zone
1,667
1.37
23
1.0%
2.1%
1.7%
73
1,233
16
36
Jack's Hut
608
1.53
7
1.3%
0.5%
0.4%
30
134
8
3
2
Parkers Hill
1,793
0.191
42
1.3%
2.1%
0.9%
11
2,443
23
38
16
TOTAL
4,501
1.13
31
1.1%
1.9%
1.1%
164
####
47
77
46
Pearse North
292
3.18
34
30
318
Southern Ore Zone
3776
1.83
17
1.0%
1.3%
1.1%
222
2017
37
51
40
Jack's Hut
1640
1.25
20
0.9%
0.8%
0.6%
66
1051
15
14
10
Parkers Hill
1843
0.19
43
1.3%
2.1%
0.9%
11
2520
23
39
17
Inferred Resource Inventory
TOTAL
7,755
1.42
26
1.0%
1.4%
0.9%
354
6,364
75
104
67
Pearse South
40
2
5
3
6
Pearse North
22
2.92
29
2
21
Southern Ore Zone
1,876
2.22
12
0.9%
0.8%
0.6%
134
706
18
14
11
Jack's Hut
1,032
1.09
28
0.7%
1.0%
0.8%
36
917
7
11
8
Parkers Hill
50
0.20
48
0.7%
1.8%
2.4%
0.3
77
0.4
1
1
3,020
1.81
18
0.9%
0.9%
0.7%
175
1,727
25
26
20
Corporate Presentation | Nov 2024
28
The Ore Reserve and Mineral Resources estimates were prepared by a Competent person in accordance with the JORC Code 2012 with exception of the Parkers
Hill Mineral Resource Estimate, which been prepared